6_ Install and tighten the nut (601).
7_ Turn the barrel of the rod (48) until the locking hook (52)
touches the roller (58).
8_ Install the new cotter pin (602).
9_ Tighten the nuts (46) and the clamp (53).
10__ Make sure that the lockwashers (47) are correctly positioned.
11__ Safety the nuts (46) and the lockwashers (47) with
MISCELLANEOUS (Material No. 19-010).
(e) Open the door and remove the shims located on the upper fittings (located on the frame).
**ON A/C ALL
Subtask 52-13-21-420-056
F. Installation of the Locking Shaft (Ref. Fig. 407/TASK 52-13-21-991-014)
(1)
Make sure that the door is closed.
(2)
Installation of the bearing assembly (110).
(a)
Apply SEALANTS (Material No. 09-018) on the surface of the bearing assembly (110) in contact with the door structure.
(b)
Install the bearing assembly (110), the bolts (111) and the nuts
(109) and tighten them.
(c)
Remove the unwanted sealant with CLEANING AGENTS (Material No. 11-004) and MISCELLANEOUS (Material No. 19-003).
(3)
Install the bush (119) and the washer (118) on the shaft upper locking (117).
(4)
Apply COMMON GREASE (Material No. 04-004) on the surface of the shaft upper locking (117).
NOTE : When you install the lever assemblies (122), (127) and (129)
____ and the bellcrank assemblies (125) and (121) on the upper locking shaft (117), make sure that the grooves are aligned.
R 1EFF : ALL 1 52-13-21Page 463 1 1 May 01/04 1 1 1CES 1
Locking Hook Adjustment
Figure 415A/TASK 52-13-21-991-030-A12 (SHEET 1)
R 1EFF : 106-149, 155-199, 208-299, 301-399, 1 52-13-21Page 464 1401-499, 1Aug 01/05 1 1 1CES 1
Locking Hook Adjustment
Figure 415A/TASK 52-13-21-991-030-A22 (SHEET 2)
R 1EFF : 106-149, 155-199, 208-299, 301-399, 1 52-13-21Page 465 1401-499, 1Aug 01/05 1 1 1CES 1
(5)
Put the shaft upper locking (117) in position.
(6)
Install the washer (120) and the bush (121).
(7)
Install the bellcrank assy (123) and the lever assembly (122).
(8)
Install the spacer (124).
(9)
Install the bellcranck assemblies (125) and (101).
(10)
Install the lever assemblies (127) and (129) and the bushes (130) and (128).
(11)
Install the washer (108) and the nut (107). NOTE : If you install a new shaft upper locking (117), drill a hole
____ of 3.7 mm (0.1456 in.) for the cotter pin installation.
(12)
TORQUE the nut (107) to between 2.2 and 2.6 m.daN (16.22 and 19.17 lbf.ft).
(13)
Install a new cotter pin (106).
(14)
Connect the rod (67).
(a)
Put the rod (67) in position in its fitting.
(b)
Install the bushes (61) and (65) with SPECIAL MATERIALS (Material No. 05-002), the washer (66) and the bolt (90).
(c)
Install the washer (64) and the nut (62).
(d)
TORQUE the nut (62) to between 0.3 and 0.35 m.daN (26.54 and
30.97 lbf.in).
NOTE : If you install a new bolt (90), drill a hole of 1.9 mm
____ (0.0748 in.) for the cotter pin installation.
(15) Connect the rod (87).
(a)
Put the rod (87) in position in its fitting.
(b)
Install the bush (88), the bolt (89), the washer (86) and the nut (84).
(c)
TORQUE the nut (84) to between 0.6 and 0.7 m.daN (53.09 and 61.94 lbf.in).
R 1EFF : ALL 1 52-13-21Page 466 1 1 Aug 01/04 1 1 1CES 1
(d) Install a new cotter pin (85). NOTE : If you install a new bolt (89), drill a hole of 2 mm
____ (0.0787 in.) for the cotter pin installation.
(16) Connect the rod (80).
(a)
Put the rod (80) in position in its fitting.
(b)
Install the bushes (79) and (81), the washer (82) and the bolt (83).
(c)
Install the washer (78) and the nut (77).
(d)
TORQUE the nut (77) to between 0.3 and 0.35 m.daN (26.54 and
30.97 lbf.in).
(e)
Install a new cotter pin (76). NOTE : If you install a new bolt (83), drill a hole of 1.9 mm