1EFF : ALL 1 52-11-11Page 461 1 1 Feb 01/04 1 1 1CES 1
(b) For the right door: 841GZ, 841FZ, 841EZ, 841DZ, 841CZ, 841BZ, 841AZ.
(4) Install the door frame lining panels (Ref. TASK 25-23-45-400-006) ( (Ref. TASK 25-23-45-400-007)).
(a) 221AW, 221BW, 221CW, 221EW, 221FW, 221GW, 221HW, 221JW, 221KW, 221LW, 221MW 221NW, 221PW, 221QW, 231AW, 231CW
(5) Install the escape slide (Ref. TASK 25-62-44-400-001). R **ON A/C 003-049, 051-099, 101-149, 151-199, 201-299, 301-399, 401-499,
Subtask 52-11-11-410-051-A
B. Installation of the Component
(1)
Remove the BALLAST WEIGHT - PASSENGER CREW DOOR (98D52103501000) (Ref. TASK 52-10-00-080-001) or the escape slide/raft (Ref. TASK 25-62-44-400-001) if previously kept in postition (as an alternative to the ballast weight).
(2)
Install the door insulation blankets.
(3)
Install the door lining panels (Ref. TASK 25-23-46-400-001).
(4)
Install the door frame lining panels.
(a)
For the left door: 221AW, 221BW, 221CW, 221EW, 221FW, 221GW, 221HW, 221JW, 221KW, 221LW, 221MW 221NW, 221PW, 221QW, 231AW, 231CW (Ref. TASK 25-23-45-400-006).
(b)
For the right: 222AW, 222BW, 222CW 222EW, 222FW, 222GW, 222HW, 222JW, 222KW, 222LW, 222MW, 222NW, 222PW, 222QW 232AW, 231CW (Ref. TASK 25-23-45-400-007).
(5)
Install the escape slide/raft (Ref. TASK 25-62-44-400-001).
1EFF : ALL 1 52-11-11Page 462 1 1 Aug 01/05 1 1 1CES 1 **ON A/C ALL
Subtask 52-11-11-410-054
C. Close Access
(1)
Obey the special precautions after the work on the door (Ref. TASK 52-10-00-860-001).
(2)
Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(3)
Make sure that the work area is clean and clear of tool(s) and other items.
(4)
Close the FWD passenger/crew door 841 (842) (Ref. TASK 52-10-00-410-001).
(5) Remove the access platform(s). Subtask 52-11-11-862-051
D. De-energize the ground service network
(Ref. TASK 24-42-00-862-001)
1EFF : ALL 1 52-11-11Page 463 1 1 Feb 01/04 1 1 1CES 1 SUSPENSION - DOOR - REMOVAL/INSTALLATION
________________________________________
TASK 52-11-12-000-001
Removal of the Door Support Arm, the Door Buffer, the Door Unlocking Handle and the Door Stay Mechanism
1. Reason for the Job
__________________
Self Explanatory
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 3.50 m (11 ft. 6 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
52-10-00-010-001 Opening of the Passenger/Crew Door 52-11-11-000-001 Removal of the FWD Passenger/Crew Door 52-11-14-000-001 Removal of the Door-Damper and Emergency-Operation
Cylinder 52-11-12-991-001 Fig. 401 52-11-12-991-002 Fig. 402 52-11-12-991-003 Fig. 403
3. Job Set-up
__________
WARNING : DO NOT OPEN THE PASSENGER/CREW DOOR IF THE WIND SPEED IS MORE THAN
_______
65 KNOTS.
WARNING : BEFORE YOU START WORK ON THE DOOR, MAKE SURE THAT:
_______
-
THE EMERGENCY CONTROL HANDLE IS IN THE DISARMED POSITION WITH THE SAFETY PIN INSTALLED.
-
THE PERCUSSION LEVER OF THE DOOR-DAMPER AND EMERGENCY-OPERATION CYLINDER IS IN THE DISARMED POSITION WITH THE SAFETY PIN INSTALLED.
1EFF : ALL 1 52-11-12Page 401 1 1 Feb 01/98 1 1 1CES 1
WARNING : STOP THE OPENING PROCEDURE IF THE RED WARNING LIGHT FLASHES.
_______ RESIDUAL PRESSURE COULD CAUSE THE DOOR TO OPEN WITH A SUDDEN FORCE AND INJURE PERSONS AND/OR DAMAGE THE AIRCRAFT.
Subtask 52-11-12-010-057
A. Get Access
(1)
Put an access platform in position in front of the applicable passenger/crew door at the zone 831 (841).