R **ON A/C 001-049, 051-099, 101-149, 201-299, 301-399,
21-52-21-991-001 Fig. 401
-------------------------------------------------------------------------------
REFERENCE DESIGNATION -------------------------------------------------------------------------------
R **ON A/C 151-199, 401-499,
R R 21-52-21-991-001-A Fig. 401A
**ON A/C ALL
21-52-21-991-002 3. Job Set-up__________ Subtask 21-52-21-861-052 Fig. 402
A. Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-002). Subtask 21-52-21-865-050
B. Open, safety and tag this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------FOR 10HM1
R **ON A/C 401-499,
R 49VU AIR COND/TEMP CTL/SYS 1 CHAN B/28VDC **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399, 52HH D08
R 122VU AIR COND/PACK TEMP/CTL SYS1/1/115VAC 122VU AIR COND/PACK TEMP/CTL SYS1/1/28VDC 1HH 3HH X22X21
R **ON A/C 001-049, 051-099, 101-105, 151-199, 201-299, 301-302,
R 122VU AIR COND/PACK TEMP CTL SYS2/1/28VDC 4HH Y19
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION
-------------------------------------------------------------------------------
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399,
R 122VU AIR COND/PACK TEMP CTL SYS2/1/115VAC 2HH Y18
R **ON A/C 106-149, 303-399,
R 122VU 4HH Y19
R **ON A/C 401-499,
R R 122VU AIR COND/TEMP CTL SYS 1/CHAN A/115VAC 122VU AIR COND/TEMP CTL SYS 1/CHAN A/28VDC 122VU AIR COND/TEMP CTL SYS 1/CHAN B/115VAC 49HH 51HH 50HH X22 X21Y18
**ON A/C ALL
FOR 11HM1
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399,
122VU AIR COND/PACK TEMP/CTL SYS1/2/115VAC 122VU AIR COND/PACK TEMP/CTL SYS1/2/28VDC 122VU AIR COND/PACK TEMP CTL SYS2/2/28VDC 122VU AIR COND/PACK TEMP CTL SYS2/2/115VAC 21HH 23HH 24HH 22HH W22W21Y21Y20
R **ON A/C 401-499,
R R 122VU AIR COND/TEMP CTL SYS 2/CHAN A/115VAC 122VU AIR COND/TEMP CTL SYS 2/CHAN A/28VDC 122VU AIR COND/TEMP CTL SYS 2/CHAN B/28VDC 122VU AIR COND/TEMP CTL SYS 2/CHAN B/115VAC 53HH 55HH 56HH 54HH W22W21 Y21Y20
**ON A/C ALL
Subtask 21-52-21-941-050
C. Safety Precautions
(1)
On the panel 30VU:
(a)
Make sure that:
-
the APU BLEED pushbutton switch is in the off position (the ON legend is off) and,
-
the ENG 1 BLEED and the ENG 2 BLEED pushbutton switches are in the off position (the OFF legends are on).
(b)
Put a warning notice in position to tell persons not to operate these pushbutton switches.
(2)
On the HP ground connector put a warning notice in position to tell persons not to supply the ground air.
Subtask 21-52-21-010-050
D. Get Access
(1)
Remove the access panel (Ref. TASK 53-35-13-000-002). FOR 10HM1 191KB, FOR 11HM1 192KB.
(2)
Remove the pipe assembly (Ref. TASK 21-52-23-000-001).
(3)
Remove the bypass valve 10HH (11HH) (Ref. TASK 21-61-53-000-001).
4. Procedure
_________
Subtask 21-52-21-020-051
A. Removal of the Air Cycle Machine R **ON A/C 001-049, 051-099, 101-149, 201-299, 301-399,
(Ref. Fig. 401/TASK 21-52-21-991-001)
Air Cycle Machine 10HM1 (11HM1).
Figure 401/TASK 21-52-21-991-001
R 1EFF : 001-049, 051-099, 101-149, 201-299, 1 21-52-21Page 405 1301-399, 1Aug 01/05 1 1 1CES 1
R **ON A/C 151-199, 401-499,
R (Ref. Fig. 401A/TASK 21-52-21-991-001-A) R
**ON A/C ALL