R 1EFF : ALL 1 12-36-29Page A375 1 1 Aug 01/00 1 1 1CES 1R Connection of the Tools to the Green Hydraulic System R Figure 321/TASK 12-36-29-991-020- 12 (SHEET 1)
1EFF : ALL 1 12-36-29Page A376 1 1 May 01/99 1 1 1CES 1R Connection of the Tools to the Green Hydraulic System R Figure 321/TASK 12-36-29-991-020- 22 (SHEET 2)
1EFF : ALL 1 12-36-29Page A377 1 1 May 01/99 1 1 1CES 1
R R Green Hydraulic System - Schematic Diagram Figure 322/TASK 12-36-29-991-021- 12 (SHEET 1)
1EFF : 1 1 1CES ALL 1 111 12-36-29 Page A378 May 01/99
R R Green Hydraulic System - Schematic Diagram Figure 322/TASK 12-36-29-991-021- 22 (SHEET 2)
1EFF : 1 1 1CES ALL 1 111 12-36-29 Page A379 May 01/99
R R R (d) Connect the connector LP1 of the TOOL - HYDRAULIC FLUID CHANGE (DH0501) to the LP connector of the hydraulic ground power supply.
R R R (e) Connect the HP1 connector of the TOOL - HYDRAULIC FLUID CHANGE (DH0501) to the HP connector of the hydraulic ground power supply.
R R (f) Connect the LP3 connector of the TOOL - HYDRAULIC FLUID CHANGE (DH0501) to the suction connector of the ground service panel.
(g) On the HP manifold (1011GM):
1_ Remove the Green HP filter (1048GM) (Ref. TASK 29-11-45-610-001).
R R R 2_ Install a dummy bowl of the TOOL - HYDRAULIC FLUID CHANGE(DH0501) in place of the Green HP filter (1048GM).
3_ Connect the HP2 line to the dummy bowl and to the valve V2.
(h) On the LP filter (1002GM):
1_ Disconnect the tube from the outlet side of the LP filter (1002GM).
2_ Put a blanking plug in the open port of the tube.
3_ Connect the LP filter (1002GM) with the LP2 line. Use the LP -HOSES FOR FLUID CHANGE (98D12308351000) for the connection.
R R (3) Start the hydraulic ground power supply and make sure that the pressure read on the gage of the TOOL - HYDRAULIC FLUID CHANGE (DH0501) is 4.0 bar (58.0150 psi).
(4) Stop the hydraulic ground power supply.
Subtask 12-36-29-611-067
F. Fill the Green Hydraulic Reservoir as follows:
(1) Open the depressurization valve (1087GM) of the Green reservoir (Ref. TASK 29-14-00-614-001).
R (2) Open the valve V1 of the TOOL - HYDRAULIC FLUID CHANGE (DH0501) and start the hydraulic ground power supply.
(3)
Fill the Green reservoir until the fluid is at the upper limit on the
visual indicator.
(4)
Close the valve V1.
(5)
Close the depressurization valve of the Green reservoir.
(6)
Pressurize the Green hydraulic reservoir (Ref. TASK 29-14-00-614-002).
(7)
Disconnect the outboard air supply.
4. Procedure
_________
Subtask 12-36-29-611-068
A. Replacement of the Hydraulic Fluid NOTE : Obey the fluid level of the Green reservoir during the procedure.
____ Adjust the fluid level with the valve V1 when it decreases.
(1) Replacement of the Fluid in the Suction, Pressure and Case Drain Lines of the Green Engine Driven Pump (1030GK):
(a) Start the hydraulic ground power supply. NOTE : Increase the rate of flow and the pressure as necessary.
____ R (b) On the TOOL - HYDRAULIC FLUID CHANGE (DH0501):
-make sure that the valve V1 is open and keep it open during the full procedure.