R 1EFF : 401-499, 1 31-60-00Page 325 1 1 Aug 01/05 1 1 1CES 1 Subtask 31-60-00-865-060
B. Make sure that this(these) circuit breaker(s) is(are) closed: -------------------------------------------------------------------------------
PANEL ------ DESIGNATION ---------------------------------------------------- IDENT. LOCATION---------------------
49VU EIS/ECAM/CTL/PNL 15WT E12
49VU EIS/DMC1/SPLY 10WT1 E11
49VU EIS/DMC3/STBY/SPLY 14WT1 E10
49VU EIS/DMC1/SWTG 21WT1 E09
49VU EIS/DMC3/SWTG 21WT3 E07
121VU EIS/DMC3/SPLY 10WT3 Q09
121VU EIS/DMC2/SPLY 10WT2 Q08
121VU EIS/DMC2/SWTG 21WT2 R08
4. Procedure_________
Subtask 31-60-00-610-054
A. X LOADING Procedure of the DMC3 from the DMC1
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. On the MCDU::
-press the line key adjacent to the EIS1 indication
2. On the MCDU:
-press the line key adjacent to the PIN PROG/STATUS AND XLOAD indication
3. On the MCDU:
-press the line key adjacent to the DMC XLOAD indication
4. On the MCDU: On the MCDU:
-
the DMC1 main menu page comes intoview. On the PFD CAPT,ND CAPT, EWD and SD Display Units:
-
the green MAINTENANCE MODE message comes into view.
On the MCDU:
-
the page DMC1 PIN PROG/STATUS ANDXLOAD comes into view
On the MCDU:
-
the page DMC1 DMC XLOAD comes intoview
-make sure that the DMC3 - software P/N is amber or empty
On the MCDU:
R 1EFF : 401-499, 1 31-60-00Page 326 1 1 Aug 01/05 1 1 1CES 1
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
-press the line key adjacent to ACCESS XLOAD
5. On the MCDU:
-press the line key adjacent to START XLOAD
6. XLOAD process
-wait for 10 minutes maximum
7. On the MCDU:
-press the line key adjacent to the RETURN indication after the delay
8. On the MCDU:
-press the line key adjacent to RETURN to get back to the main menu page
5. Close-up
________
Subtask 31-60-00-860-089
-
the page DMC1 DMC XLOAD comes intoview
On the MCDU:
-
the page DMC1 DMC XLOAD comes intoview with the message TRANSFER IN PROGRESS DMC1 to DMC3 (MAX 10 MINUTES)
On the MCDU:
-
the page DMC1 DMC XLOAD is displayed with the message INTEGRITY CHECK
-On the CAPT PFD, CAPT ND, EWD and SD display units:
-make sure that the message MAINTENANCE MODE comes into view
-
the page DMC1 DMC XLOAD is displayed with the message DMC3 XLOAD COMPLETED in green and the message DMC SELF TEST IN PROGRESS 40s also in green
On the MCDU:
-
the page DMC1 DMC XLOAD comes intoview with the newly installedsoftware P/N displayed in green on the line DMC3
A. Put the aircraft back to its initial configuration.
(1)
Do the EIS stop procedure (Ref. TASK 31-60-00-860-002).
(2)
Make sure that the work area is clean and clear of tool(s) and other items.
R 1EFF : 401-499, 1 31-60-00Page 327 1 1 Aug 01/05 1 1 1CES 1 (3) De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002).
R 1EFF : 401-499, 1 31-60-00Page 328 1 1 Aug 01/05 1 1 1CES 1 TASK 31-60-00-610-006
1. Reason for the Job
UP LOADING Procedure of the DMC1 with a portable DATA LOADER __________________ Self Explanatory
2. Job Set-up Information______________________
A. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power
24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power
31-32-00-860-008 Procedure to Get Access to the SYSTEM
REPORT/TEST/INST Page 31-60-00-860-001 EIS Start Procedure 31-60-00-860-002 EIS Stop Procedure
3. Job Set-up
__________ Subtask 31-60-00-869-070
A. Aircraft Maintenance Configuration
(1)
Energize the aircraft electrical circuits
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 指示/记录系统 7(73)