PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------R **ON A/C 106-149, 303-399, 401-499,
49VU EIS/PFD/CAPT/SPLY 11WT1 E03
**ON A/C ALL
FOR 2WT2 121VU EIS/PFD/F/O/SWTG 22WT2 R05 121VU EIS/PFD/F/O 11WT2 R03
FOR 3WT1 49VU EIS/ND CAPT/SWTG 23WT1 E02 49VU EIS/ND CAPT/SPLY 12WT1 E01
FOR 3WT2 121VU EIS/ND/F/O/SWTG 23WT2 R06 121VU EIS/ND/F/O 12WT2 R04
FOR 4WT1 49VU EIS/ECAM DU/UPPER/SWTG 24WT1 E06 49VU EIS/ECAM DU/UPPER/SPLY 13WT1 E05
FOR 4WT2 121VU EIS/ECAM DU/LOWER/SPLY 13WT2 R11 121VU EIS/ECAM DU/LOWER/SWTG 24WT2 R10
4. Procedure
_________
(Ref. Fig. 401/TASK 31-63-22-991-001)
Subtask 31-63-22-020-050
A. Removal of the Display Unit
(1) FOR 2WT1, 3WT1 Remove the thermoformed cover from the CAPT main instrument panel. FOR 2WT2, 3WT2 Remove the thermoformed cover from the F/O main instrument panel. FOR 4WT1, 4WT2 Remove the thermoformed cover from the center instrument panel.
1EFF : ALL 1 31-63-22Page 402 1 1 Aug 01/05 1 1 1CES 1
Display Unit.
Figure 401/TASK 31-63-22-991-001
1EFF : ALL 1 31-63-22 Page 403
1 1 Feb 01/98
1 1
1CES 1
(2)
Push in the two locking catches (4).
(3)
If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
(4)
Slowly and continuously lower the handle (3) to the bottom section of the screen : at the same time, the unit (2) moves out from the panel by approximately 3 cm.
(5)
Pull the handle (3) found at the removal point and disengage the unit (2).
(6)
Remove the unit (2).
(7)
Put blanking caps on the electrical connectors (1).
(8)
Put the unit in the replacement unit container.
1EFF : ALL 1 31-63-22Page 404 1 1 Feb 01/05R 1 1 1CES 1
TASK 31-63-22-400-001
Installation of the Display Unit (2WT1,2WT2,3WT1,3WT2,4WT1,4WT2)
1. Reason for the Job
__________________
Self Explanatory
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
22-97-00-710-001 Operational Test of the LAND CAT III Capability 31-60-00-610-001 X LOADING Procedure of the DMC1 to the PFD CAPT, ND CAPT, the EWD or the SD 31-60-00-610-002 X LOADING Procedure of the DMC2 to the PFD F/O or the
ND F/O 31-60-00-710-001 Operational Test of the EIS 31-60-00-860-001 EIS Start Procedure 52-41-00-410-002 Close the Avionics Compartment Doors after Access 31-63-22-991-001 Fig. 401
3. Job Set-up
__________
Subtask 31-63-22-865-051
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------FOR 2WT1
R **ON A/C 001-049, 051-099, 101-105, 151-199, 201-299, 301-302,
49VU EIS/PFD CAPT/SPLY 11WT1 E03
**ON A/C ALL
49VU EIS/PFD CAPT/SWTG 22WT1 E04
1EFF : ALL 1 31-63-22Page 405 1 1 May 01/05 1 1 1CES 1 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------
R **ON A/C 106-149, 303-399, 401-499,
49VU EIS/PFD/CAPT/SPLY 11WT1 E03
**ON A/C ALL
FOR 2WT2 121VU EIS/PFD/F/O/SWTG 22WT2 R05 121VU EIS/PFD/F/O 11WT2 R03
FOR 3WT1 49VU EIS/ND CAPT/SWTG 23WT1 E02 49VU EIS/ND CAPT/SPLY 12WT1 E01
FOR 3WT2 121VU EIS/ND/F/O/SWTG 23WT2 R06 121VU EIS/ND/F/O 12WT2 R04
FOR 4WT1 49VU EIS/ECAM DU/UPPER/SWTG 24WT1 E06 49VU EIS/ECAM DU/UPPER/SPLY 13WT1 E05
FOR 4WT2 121VU EIS/ECAM DU/LOWER/SPLY 13WT2 R11 121VU EIS/ECAM DU/LOWER/SWTG 24WT2 R10
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 指示/记录系统 7(160)