 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific blanking caps
 No specific container
 No specific warning notices
 No specific access platform 2.8 m (9 ft. 2 in.)

R No specific Torque Wrench : range 0.00 to 1.20 m.daN R (0.00 to 9.00 lbf.ft) No specific Torque Wrench : range 1.00 to 10.00 m.daN
 (8.00
 to 75.00 lbf.ft) No specific Torque Wrench : range 2.00 to 20.00 m.daN

 (15.00 to 150.00 lbf.ft)

 B.
 Consumable Materials


 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
No specific  lockwire, corrosion resistant steel 0.8 mm (0.032 in.).
 Material No. 02-003  F NSA 307110 TYPE 4
 HYDRAULIC FLUID (PHOSPHATE ESTER BASE)
 (Ref. 20-31-00)

 

 C. Expendable Parts
 -------------------------------------------------------------------------------
FIG.ITEM |DESIGNATION |IPC-CSN
 -------------------------------------------------------------------------------
6 O-ring 29-11-03 05A-070 6 O-ring 29-11-03 05B-070 10 O-ring 29-11-03 05A-090 10 O-ring 29-11-03 05B-090
 D. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION
 -------------------------------------------------------------------------------
12-12-29-611-001 Fill the Hydraulic Fluid Reservoir with a Hand Pump 12-14-29-614-001 Fill the Hydraulic Power Accumulators 1070GM/2070GM/3070GM with Nitrogen 29-00-00-864-001 Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action 29-00-00-870-003 Bleeding Procedure of the Green Hydraulic System
 Downstream of the Engine Pump 29-00-00-910-002 Safety Procedures of the Hydraulic System 29-10-00-863-001 Pressurize the Green Hydraulic System 29-14-00-614-001 Depressurization of the Hydraulic Reservoirs 29-14-00-614-002 Pressurization of the Hydraulic Reservoirs through
 the Ground Connector 29-23-00-860-001 Disconnection of the Isolation Coupling of the Power Transfer Unit (PTU) 29-23-00-860-002 Connection of the Isolation Coupling of the Power
 Transfer Unit (PTU)
 32-12-00-010-001 Open the Main Gear Doors for Access
 32-12-00-410-001 Close the Main Gear Doors after Access

 **ON A/C 001-001, 051-052,
 29-11-42-991-001 Fig. 401
R **ON A/C 002-049, 053-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 29-11-42-991-001-A Fig. 401A **ON A/C ALL


 3. Job Set-up
__________ Subtask 29-11-42-860-052
 A. Aircraft Maintenance Configuration
 WARNING : OBEY THE HYDRAULIC SAFETY PROCEDURES.

_______
 (1)
 Obey the hydraulic safety procedures (Ref. TASK 29-00-00-910-002).

 (2)
 Make sure that the Green hydraulic system is depressurized and put it in the maintenance configuration. (Ref. TASK 29-00-00-864-001).

 (3)
 Make sure that the reservoir of the Green hydraulic system is depressurized. (Ref. TASK 29-14-00-614-001).

 (4)
 Make sure that the warning notices are in position to tell persons not to pressurize the Green hydraulic system:

 -in the cockpit on the hydraulic section 40VU of the overhead panel, - on the ground service panel of the Green hydraulic system.

 (5)
 Make sure that the left main door of the main gear is open (Ref. TASK 32-12-00-010-001).

 (6)
 Make sure that the access platform is in position at the main doors of the main gear.

 (7)
 Make sure that the isolation coupling of the Power Transfer Unit (PTU) is disconnected (Ref. TASK 29-23-00-860-001).

 (8)
 Make sure that the container is in position below the accumulator connections.

 


 Subtask 29-11-42-865-051
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
 -------------------------------------------------------------------------------
PANEL DESIGNATION IDENT. LOCATION
 -------------------------------------------------------------------------------
121VU HYDRAULIC/HYD POWER/Y 3803GX N30 123VU Y HYD/ELEC/PUMP 3802GX AB06 123VU Y HYD/ELEC/ELEC PUMP/NORM 3801GX AB03
 4. Procedure
_________
 **ON A/C 001-001, 051-052,

 (Ref. Fig. 401/TASK 29-11-42-991-001) R **ON A/C 002-049, 053-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 (Ref. Fig. 401A/TASK 29-11-42-991-001-A)
 