F.
Operation Force of the Flap Control Lever - Test
S 735-043
(1)
Do the test as follows:
(a)
Measure the force necessary to move the flap control lever smoothly from the zero (FLAPS UP) detent to the 30-unit detent in five seconds.
(b)
Make sure the force does not exceed nine pounds.
(c)
Move the flap control lever to the 1-unit detent.
(d)
Let the flaps and slats stop at the 1-unit position.
(e)
Move the flap control lever to zero (FLAPS UP) detent.
(f)
Make sure the force necessary to move the flap control lever is less than six and one-half pounds.
G.
FSEU BITE - Test (-17 or lower FSEU's)
S 745-044
(1)
Do the FSEU BITE procedure as follows:
(a)
Put the EICAS computer switch on the EICAS DISPLAY select-panel, P9, to L.
(b)
Do the BITE test on the FSEU-1 in the main equipment center as follows: 1) Push the BIT test switch. 2) Make sure all the lights on the FSEU panel face come on. 3) Release the BIT test switch. 4) Make sure all the lights on the FSEU panel face go off. 5) Make sure that no FAULT indications occur. 6) Make sure the green TEST COMPLETE light comes on. 7) Make sure the indications that follow come on momentarily
in the sequence shown while the BITE test is run:
EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
27-51-00
ALL ú ú 01 Page 525 ú May 20/98
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
(c)
(d)
757 MAINTENANCE MANUAL
~.............................................
| INDICATION | LOCATION |
...............................................
| TRAILING EDGE LIGHT | P3 |
...............................................
| LEADING EDGE LIGHT | P3 |
...............................................
| TE FLAP DISAGREE | UPPER EICAS SCREEN |
...............................................
| TE FLAP ASYM | UPPER EICAS SCREEN |
...............................................
| LE SLAT DISAGREE | UPPER EICAS SCREEN |
...............................................
| LE SLAT ASYM | UPPER EICAS SCREEN |
...............................................
| FLAP LOAD RELIEF | UPPER EICAS SCREEN |
...............................................
| FLAP/SLAT ELEC *[1] | EICAS STATUS PAGE |
2.......................….....................1
*[1] The EICAS status page must be on for the message to show.
Push the arming switch for the alternate drive of the LE slats
to arm the slat alternate drive (switch light will come on).
Do the BITE test on the FSEU-2 in the main equipment center as
follows:
1) Push the BIT test switch.
2) Make sure all the lights on the FSEU panel face come on.
3) Release the BIT test switch.
4) Make sure all the lights on the FSEU panel face go off.
5) Make sure that no FAULT indications occur.
6) Make sure the green TEST COMPLETE light comes on.
7) Make sure the indications that follow come on momentarily in the sequence shown while the BITE test is run:
EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
27-51-00
ALL ú ú 01 Page 526 ú Jan 28/01
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
757 MAINTENANCE MANUAL
~............................................. | INDICATION | LOCATION | ............................................... | TRAILING EDGE LIGHT | P3 | ............................................... | LEADING EDGE LIGHT | P3 | ............................................... | TE FLAP DISAGREE | UPPER EICAS SCREEN | ............................................... | TE FLAP ASYM | UPPER EICAS SCREEN | ............................................... | LE SLAT DISAGREE | UPPER EICAS SCREEN | ............................................... | LE SLAT ASYM | UPPER EICAS SCREEN | ............................................... | FLAP LOAD RELIEF | UPPER EICAS SCREEN | ............................................... | FLAP/SLAT ELEC *[1] | EICAS STATUS PAGE | 2.......................….....................1
中国航空网 www.aero.cn