EFF : ALL
25-21-00Page 601
R R (4) Make sure that the seat belt attachments,the seat belts and the buckles are in the correct condition and location.
R (5) Make sure that the seat belt locking system opperates correctly.
5. Close-up________
Subtask 25-21-00-210-051
A. Close Access
(1) Make sure that the work area is clean and clear of tool(s) and other items.
Subtask 25-21-00-862-050
B. De-energize the ground service network (Ref. TASK 24-42-00-862-001)
EFF : ALL
25-21-00Page 602
TASK 25-21-00-210-002
R Detailed Visual Inspection of Seat Belts Attachment, Seat Belts and Locks Check R of Locks
1.
Reason for the Job
__________________
Refer to the MPD TASK: 252100-02
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from the External Power
3. Job Set-up
__________ Subtask 25-21-00-861-051 R A. Energize the ground service network (Ref. TASK 24-42-00-861-001)
4. Procedure
_________
Subtask 25-21-00-210-052
A. Visual Inspection/Check Passenger-Seats Seat Belts
(1)
Make sure that the seat belt attachments, the seat belts and the buckles are in the correct condition.
(2)
Make sure that the operation of the seat belt locking/unlocking system is correct.
EFF : ALL
25-21-00Page 603
R 5. Close-up________
Subtask 25-21-00-210-053
A. Close Access
(1) Make sure that the work area is clean and clear of tool(s) and other items.
R Subtask 25-21-00-862-051
R R B. De-energize the ground service network (Ref. TASK 24-42-00-862-001)
EFF : ALL
25-21-00Page 604
MASTER CONTROL UNIT - SEAT POWER SUPPLY (55HP) - REMOVAL/INSTALLATION
_____________________________________________________________________ TASK 25-21-34-000-001 Removal of the Master Control Unit (MCU)
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific blanking caps
No specific circuit breaker(s) safety clip(s)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 25-21-34-991-001 Fig. 401
3. Job Set-up
__________ Subtask 25-21-34-861-050
A. Energize the ground service network
(Ref. TASK 24-42-00-861-001).
Subtask 25-21-34-010-050
B. Get Access
(1)
Open the door of the related overhead stowage compartment.
(2)
Remove the cover.
R **ON A/C 301-399,
Subtask 25-21-34-865-050
C. Open, safety and tag this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL DESIGNATION FIN LOCATION -------------------------------------------------------------------------------2000VU PED 50HP B8
R **ON A/C 301-399, 401-499,
4. Procedure
_________
Subtask 25-21-34-020-050
A. Removal of the Master Control Unit (MCU) 55HP 中国航空网 www.aero.cn 航空翻译 www.aviation.cn 本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备1(138)