(2)
Make sure that the Captain (First Officer) seat cushion is removed (Ref. TASK 25-11-61-000-001).
EFF : ALL
25-11-69Page 405
Subtask 25-11-69-865-051
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------FOR 3MS
122VU COCKPIT SEATS/SEAT CTL/CAPT 1MS1 U11
122VU LIGHTING/FLOOD/CAPT/SIDE 5LE Z05
FOR 4MS 122VU COCKPIT SEATS/SEAT CTL/F/O 1MS2 U14 122VU LIGHTING/FLOOD/F/O/SIDE 4LE Z06
4. Procedure
_________
(Ref. Fig. 401/TASK 25-11-69-991-001) Subtask 25-11-69-420-050
A. Installation of the Captain (First Officer) Seat Pan and Base Accessories
(1)
Connect the switch lugs to the switches (16). NOTE : Refer to the marks when you connect the switch lugs.
____
(2)
Install the plate (19) on the switches (16).
(3)
Install the washers (20), (21) and the nuts (22) and tighten them.
(4)
Install the electrical control switches (24) and the screws (23) and tighten them.
(5)
Install the switch cover (30) on the seat pan (27) and on the plate (19).
(6)
Install the screws (31), the washers (32) and tighten them.
(7)
Install the bonding lead (11), the screw (10), the washer (12) and the nut (13).
(8)
Safety the nut (13) with BONDING AND ADHESIVE COMPOUNDS (Material No. 08-007) and tighten the screw (10).
NOTE : Make sure that you do the electrical bonding when you install
____ the bonding lead (Ref. TASK 20-28-00-912-001).
EFF : ALL
25-11-69Page 406
(9) Install the bonding lead (29), the screw (28), the washer (17) and the nut (18).
(10) Safety the nut (18) with BONDING AND ADHESIVE COMPOUNDS (Material No. 08-007) and tighten the screw (28).
NOTE : Make sure that you do the electrical bonding when you install
____ the bonding lead (Ref. TASK 20-28-00-912-001).
(11)
Install the wiring cover (3), the screws (4), (6), the washers (5) and the nuts (15) and tighten them.
(12)
Install the wiring cover (9), the screws (7), the washers (8) and the nuts (14) and tighten them.
(13)
Install the "H", "V" and "R" control levers (25) and the socket head screws (26) and tighten them.
(14)
Push the dust covers (1) down to install them on the base assy (2).
5. Close-up
________ Subtask 25-11-69-410-050
A. Installation of Seat Equipment
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Install the Captain (First Officer) seat cushion (Ref. TASK 25-11-61-400-001).
Subtask 25-11-69-865-052
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): FOR 3MS 1MS1, 5LE. FOR 4MS 1MS2, 4LE.
Subtask 25-11-69-862-050
C. De-energize the ground service network
(Ref. TASK 24-42-00-862-001).
EFF : ALL
25-11-69Page 407
LINING AND FURNISHINGS - DESCRIPTION AND OPERATION
__________________________________________________
1.
General
_______ (Ref. Fig. 001) The heat and sound insulation blankets are covered by lining and furnishing panels, which also provide cockpit decoration. The lining panels are easily removable, so as to enable access to the installations behind these panels. Various furnishings are fitted in the cockpit for the comfort, convenience and safety of the crew.
2.
Description
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备1(118)