Subtask 25-13-14-860-055
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. TASK 24-42-00-861-001)
EFF : ALL
25-13-14Page 601
4. Procedure
_________ (Ref. Fig. 601/TASK 25-13-14-991-005) Subtask 25-13-14-020-055
A. Removal of the foot rest and sliding table assembly (Ref. TASK 25-13-14-000-001).
Subtask 25-13-14-210-050
B. Inspection of the Foot Rest Actuators
(1)
Put the foot rest assembly (1) on a bench, with the foot rest on the top and in the stowed position.
(2)
Make sure that the retaining rings (2) and (3) are in position and correctly installed.
(3)
Make sure that the pins (4) and (5) are correctly installed and not damaged.
(4) Replace all the missing, broken or damaged retaining rings or pins. Subtask 25-13-14-420-055
C. Installation of the foot rest and sliding table assembly (Ref. TASK 25-13-14-400-001).
5. Close-up
________ Subtask 25-13-14-942-054
A. Make sure that the work area is clean and clear of tool(s) and other items.
Subtask 25-13-14-860-056
B. Aircraft Maintenance Configuration
(1) De-energize the ground service network (Ref. TASK 24-42-00-862-001)
Inspection of the Foot Rest Actuator Figure 601/TASK 25-13-14-991-005
R EFF : 001-049, 051-061, 101-103, 201-203, 25-13-14 Page 603 May 01/05
CES
R **ON A/C ALL
R TASK 25-13-14-200-002 R Visual Inspection of the Foot Rest Actuator R 1. Reason for the Job
__________________ R Self Explanatory R 2. Job Set-up Information
______________________
R A. Referenced Information
R -------------------------------------------------------------------------------R REFERENCE DESIGNATION R -------------------------------------------------------------------------------
R 24-42-00-861-001 R R 24-42-00-862-001 R R 25-13-14-991-006
R 3. Job Set-up
__________
R Subtask 25-13-14-860-057 Energize the Ground Service Network from the External Power De-energize the Ground Service Network Supplied from the External Power Fig. 602
R A. Aircraft Maintenance Configuration
R (1) Energize the ground service network R (Ref. TASK 24-42-00-861-001) R 4. Procedure
_________
R Subtask 25-13-14-210-051
R A. Inspection of the Foot Rest Actuator
R (Ref. Fig. 602/TASK 25-13-14-991-006)
R (1) On the foot rest assembly (1), push the foot rest (2) down.
R (2) Release pressure and let the foot rest come back to its stowed
R position.
R (3) Make sure that the foot rest (2) is against the stop (3).
EFF : ALL
25-13-14Page 604
Nov 01/00
R R Visual Inspection of the Foot Rest Actuator Figure 602/TASK 25-13-14-991-006
EFF : ALL 25-13-14 Page 605 Nov 01/00
CES
R (4) If the foot rest (2) is not against the stop (3), replace the
R actuator (4).
R (5) Do the same operation for each foot rest assembly.
R 5. Close-up________
R Subtask 25-13-14-942-055
R A. Make sure that the work area is clean and clear of tool(s) and other
R items.
R Subtask 25-13-14-860-058
R B. Aircraft Maintenance Configuration
R (1) De-energize the ground service network (Ref. TASK 24-42-00-862-001)
EFF : ALL
25-13-14Page 606
Nov 01/00
LINING PANELS - REMOVAL/INSTALLATION
____________________________________
TASK 25-13-41-000-001 Removal of the Ceiling Panels
1. Reason for the Job
__________________
Self Explanatory
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific circuit breaker(s) safety clip(s)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
25-13-41-991-001 Fig. 401
3. Job set up
__________ Subtask 25-13-41-865-050
A. Open, safety and tag this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------49VU LIGHTING/EMER LT/CKPT/DOME 1LE H08 122VU LIGHTING/CKPT/DOME 3LE Y06