 Operational Test of the In-Seat Power-Supply System (PED Power Supply)
 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------
REFERENCE  QTY DESIGNATION
 -------------------------------------------------------------------------------
No specific  1 MULTIMETER - STANDARD
 B. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE  DESIGNATION
 -------------------------------------------------------------------------------
24-41-00-861-002  Energize the Aircraft Electrical Circuits from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power R 35-23-00-710-001 Operational Check of Manual Mask Release
 3. Job Set-up
__________
 Subtask 25-21-00-861-053

 A. Energize the aircraft electrical circuits
 (Ref. TASK 24-41-00-861-002).

 

 4. Procedure
_________ Subtask 25-21-00-710-053
 A. Operational Test of the PED Power Supply:
 (1)
 In the FWD cabin area:

 -Make sure that the PED power ON/OFF switch is in the OFF position.

 (2)
 Connect a MULTIMETER - STANDARD together with a consumer/resistor to the portable electrical device (PED) power-outlet of a passenger seat.


 NOTE : A minimum load of 3W is required, if not the outlet unit will
____
 be disabled.

 NOTE : The red LED (if installed) of the seat power outlet is on, the
____
 multimeter shows 0 VAC.

 (3) Do this test:
 -------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. In the FWD cabin area:
-Set the PED power ON/OFF switch to the ON position.
2. In the cockpit:
-Do the operational test of the passenger emergency-oxygen system (Ref. TASK 35-23-00-710-001).
NOTE : Do not hold the MASK MAN
____ ON pushbutton switch for more than 30 sec., because the FAULT indication light in the TMR RESET pushbutton switch comes on after 30 sec.
 In the cockpit:
-Immediately reset the passenger emergency-oxygen system (Ref. TASK 35-23-00-710-001).
At the seat power outlet:
-
The green LED (if installed) comes on

-
The multimeter shows 110 +15-6VAC.

At the seat power outlet:

-
The red LED (if installed) comes on.

-
The multimeter shows 0 VAC.


NOTE : The red LED (if installed) of
____ the power outlet stays on andthe multimeter shows 0 VDC untilyou reset the emergency-oxygensystem.
At the seat power outlet:
-
The green LED (if installed) comes on

-
The multimeter shows 110 +15-6VAC.

 


 -------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
3. In the FWD cabin area:  At the seat power outlet:
 -Set the PED power ON/OFF switch  - The red LED (if installed) comes on. to the OFF position. - The multimeter shows 0 VAC.
 (4) Disconnect the multimeter from the power outlet of the passenger seat.
 NOTE : The red LED (if installed) of the power outlet stays on until
____ the aircraft electrical network is de-energized.
 (5) Make sure that the work area is clean and clear of tool(s) and other items.
 5. Close-up
________
 Subtask 25-21-00-862-053
 A. De-energize the aircraft electrical circuits
 (Ref. TASK 24-41-00-862-002).

 

 PASSENGER COMPARTMENT SEATS - INSPECTION/CHECK
______________________________________________ TASK 25-21-00-210-001 R Detailed Inspection of Seat to Floor Attachment and General Visual Inspection of Seats Structure
 1.
 Reason for the Job

__________________
 Refer to the MPD TASK: 252100-01


 2.
 Job Set-up Information


______________________
 A. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 24-42-00-862-001
3. Job Set-up
__________ Subtask 25-21-00-861-050
Energize the Ground Service Network from the External PowerDe-energize the Ground Service Network Supplied from the External Power
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备1(137)