2. Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION
 -------------------------------------------------------------------------------
No specific warning notice
 No specific access platform 1.5 m (4 ft. 11 in.)
 B. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
71-13-00-010-040 Opening of the Fan Cowl Doors 71-13-00-410-040 Closing of the Fan Cowl Doors 71-73-49-000-006 Removal of the Oil Tank Drain Tube and Hose 71-73-49-400-006 Installation of the Oil Tank Drain Tube and Hose 78-30-00-081-041 Make the Thrust Reverser Serviceable after
 Maintenance 78-30-00-481-041 Make the Thrust Reverser Unserviceable for
 Maintenance 78-36-00-010-040 Opening of the Thrust Reverser Doors 78-36-00-410-040 Closing of the Thrust Reverser Doors
 F 『 EEFF : ALL E Page 60171-73-49
 E E Feb 01/98 E E ECES E
 F 『
 E C F M E
 E E
 E 56-5B E
 E E
 3. Job Set-up
__________
 Subtask 71-73-49-941-051
 A. Safety Precautions
 (1) On the center pedestal, on the ENG panel 115VU:
(a) Put a warning notice to tell persons not to start the engine.
(2) Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
(3) On the overhead maintenance panel 50VU:
(a) Make sure that the ON legend of the ENG/FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put a warning notice to tell persons not to energize the FADEC 1(2).
 Subtask 71-73-49-010-052
 B. Get Access
 (1) Open the fan cowl doors (Ref. TASK 71-13-00-010-040):
 FOR 1000EM1
 437AL, 438AR
 FOR 1000EM2
 447AL, 448AR
 (2) Put the access platform in position.
 Subtask 71-73-49-040-050
 C. Make the thrust reverser unserviceable (Ref. TASK 78-30-00-481-041).
 Subtask 71-73-49-010-051
 D. Open the thrust reverser doors (Ref. TASK 78-36-00-010-040):
 FOR 1000EM1
 451AL, 452AR
 FOR 1000EM2
 461AL, 462AR
 F 『 EEFF : ALL E Page 60271-73-49
 E E Feb 01/98 E E ECES E
 F  『 
 E  C F M  E 
 E  E
 E 56-5B E
 E E
 Subtask 71-73-49-020-051
 E. Removal of the Oil, Hydraulic and Water Drain Tubes and Hose (Ref. TASK 71-73-49-000-006).
 4. Procedure
_________ Subtask 71-73-49-210-050
 A. Inspection of the Oil, Hydraulic and Water Tubes and Hose
 (1) Examine the tube/hose and make sure that there is nothing in the tube to block the flow through the tube/hose.
(2) Examine the tube/hose to make sure that it is not cracked or dented.
(3) Examine the tube/hose for wear and corrosion.
(4) Examine the tube/hose end fittings to make sure that they are attached correctly.
(5) Examine the fittings on the two ends of the tube/hose to make sure that they are not cracked or dented.
(6) Examine the threads on the end fittings for damage.
(7) Examine the tube/hose end fittings to make sure that they are clean.
(8) If applicable, examine all welded joints for cracks, corrosion, and wear.
 5. Close-up
________ Subtask 71-73-49-420-051
 A. Install the Oil, Hydraulic and Water Drain Tubes and Hose (Ref. TASK 71-73-49-400-006).
 F 『 EEFF : ALL E Page 60371-73-49
 E E Feb 01/98 E E ECES E Subtask 71-73-49-410-051
 F  『 
 E  C F M  E 
 E  E 
 E  56-5B  E 
 E  E
 B. Close Access
 (1) Make sure that the work area is clean and clear of tool(s) and other items.
(2) Close the thrust reverser doors (Ref. TASK 78-36-00-410-040): FOR 1000EM1 451AL, 452AR FOR 1000EM2 461AL, 462AR
 (3) Remove the access platform(s). Subtask 71-73-49-440-050
C. Make the thrust reverser serviceable (Ref. TASK 78-30-00-081-041). Subtask 71-73-49-410-052
 D. Close Access
 (1) Close the fan cowl doors (Ref. TASK 71-13-00-410-040):
 FOR 1000EM1
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 动力装置 POWER PLANT 2(132)