De-energize the aircraft electrical circuits supplied from the external power (Ref. TASK 24-41-00-862-002).
(3)
Close the passenger/crew doors (Ref. TASK 52-10-00-410-001).
(4)
Close the FWD and AFT cargo-compartement doors (Ref. TASK 52-30-00-860-002).
(5)
Close the emergency exit doors (Ref. TASK 52-22-00-410-001).
(6)
Seal with STORAGE PRESERVATION (Material No. 15-002) and adhesive tape:
-
the avionics ventilation system inlets and outlets (15HQ and 22HQ)
-
the outflow valve (10HL)
-
the doors and the handles.
(7)
Remove all the fixtures, tools, test and support equipment used during this procedure.
INTENTIONALLY BLANK
R
10-12-00Page 612
May 01/04 CES R **ON A/C ALL
R TASK 10-12-00-200-009 R Periodic ground-check at 3-month interval R 1. Reason for the Job
__________________ R To do a check of the condition of the aircraft during the storage period. R 2. Job Set-up Information
______________________ R A. Fixtures, Tools, Test and Support Equipment R -------------------------------------------------------------------------------
R REFERENCE QTY DESIGNATION R -------------------------------------------------------------------------------R No specific 1 ACCESS PLATFORM 15M (49 FT) - ADJUSTABLE
R B. Consumable Materials R -------------------------------------------------------------------------------R REFERENCE DESIGNATION R -------------------------------------------------------------------------------
R Material No. 04-011 R R R Material No. 05-005 R R Material No. 05-027 R R R Material No. 11-002 R R R Material No. 15-002 R
USA MIL-G-4343
SILICONE GREASE PNEUMATIC SYST AND SEALS
(Ref. 20-31-00)
USA MIL-C-16173 GRADE II
CORROSION PREVENTIVE (Ref. 20-31-00)
USA MIL-L-81309
RUST INHIBITOR(FOR CORROSION USE 15-004)
(Ref. 20-31-00)
USA MIL-PRF-680
DRY CLEANING SOLVENT (VARSOL/WHITE SPIRIT)
(Ref. 20-31-00)
USA MIL-B-131 TYPE I
BARRIER MATERIAL WATER VAPOR PROOF (Ref. 20-31-00)
R C. Referenced Information
R -------------------------------------------------------------------------------R REFERENCE DESIGNATION R -------------------------------------------------------------------------------
R 05-27-10-200-001
R 05-27-30-200-001
R 07-12-00-582-001
R 07-12-00-582-002
R 10-20-00-556-001
R 12-21-11-615-001
R 24-41-00-861-002
R
R 24-41-00-862-002
R
R 27-14-00-710-001
R
R 27-24-00-710-001
R 27-34-00-710-001
R
R 27-54-00-710-001
R 27-64-00-710-001
R 27-84-00-710-001
R 28-23-00-720-001
R
R 28-24-00-710-002
R
R 28-29-00-710-001
R
R 29-10-00-200-001
R 29-10-00-863-003
R
R 29-10-00-864-003
R 29-23-00-863-001
R
R
R 29-23-00-864-001
R
R 29-24-00-863-001
R
R 29-24-00-864-001
R 32-31-00-710-002
R 51-74-11-300-001
R 53-59-00-210-001
R
R 54-50-00-200-001
Zonal Inspection of Nose Gear and Nose Gear Doors Zonal Inspection of LH/RH Main Landing Gear Jacking for Nose Gear Wheel Change Jacking for Main Gear Wheel Change Mooring of the Aircraft External Cleaning Energize the Aircraft Electrical Circuits from the External Power De-energize the Aircraft Electrical Circuits Supplied from the External Power Operational Test of the Aileron and Hydraulic Actuation Operational Test of the Rudder Hydraulic Actuation Operational Test of the Elevator and Hydraulic Actuation Operational Test of the Flap System Operational Test of the Spoiler Hydraulic Actuation Operational Test of the Slat System Operational Test of Crossfeed Valve Using Individual Motors: ... Operational Test of the ENG 1(2) LP Fuel Valve 12QM (13QM) Operational Test of the APU Low Pressure Fuel Valve using each individual Motor in turn Check Fluid Level on Reservoir Indicators Pressurize the Blue Hydraulic System with a Ground Power Supply Depressurize the Blue Hydraulic System Pressurize the Green Hydraulic System from the Yellow Hydraulic System through the PTU with the Electric Pump Depressurize the Green and Yellow Hydraulic Systems after Operation of the PTU Pressurize the Yellow Hydraulic System with the Electric Pump Depressurize the Yellow Hydraulic System Operational Test of the Landing Gear Doors Repair of Corroded Areas Operational Check of Single Drain Pipe Aft of FR70 from Outside General Inspection of the Pylon Drain System 中国航空网 www.aero.cn 航空翻译 www.aviation.cn 本文链接地址:A320飞机维护手册 AMM PARKING, MOORING, STORAGE & RETURN TO S(43)