REFERENCE DESIGNATION -------------------------------------------------------------------------------
29-23-00-863-001 
29-23-00-864-001 
29-24-00-863-001 
29-24-00-864-001 30-45-00-040-002 30-45-52-000-002 30-45-53-000-001 31-33-55-000-001 32-00-00-481-001 
32-12-00-010-001 32-12-00-410-001 32-22-00-010-001 32-22-00-410-001 32-40-00-200-001 32-41-00-210-003 32-41-11-400-006 
R  32-41-12-400-001 32-48-51-000-005 33-51-38-000-002 
34-10-00-170-001 34-10-00-170-002 34-10-00-170-003 34-22-25-170-001 
R R R  49-20-00-200-001 49-20-00-210-001 49-20-00-600-001 49-20-00-600-002 
49-20-00-600-003 
52-10-00-010-001 52-10-00-410-001 52-22-00-010-001 

Pressurize the Green Hydraulic System from the Yellow Hydraulic System through the PTU with the Electric PumpDepressurize the Green and Yellow Hydraulic Systems after Operation of the PTUPressurize the Yellow Hydraulic System with the Electric PumpDepressurize the Yellow Hydraulic SystemDeactivation of the Rain Repellent SystemRemoval of the Wiper Arm (306DM, 307DM)Removal of the Wiper BladeRemoval of the Digital Flight Data Recorder (DFDR)Installation of the Safety Devices on the Landing GearsOpen the Main Gear Doors for AccessClose the Main Gear Doors after AccessNose Gear Doors - Ground Doors OpeningNose Gear Doors - Ground Doors ClosingInspection/Check of the Wheels & BrakesInspection/Check of the Pressure of TiresInstallation of the MLG Wheel (2649GM,2650GM,2651GM,2652GM)Installation of the NLG Wheel (2659GM,2660GM) Removal of the Fan Assy (7GS,8GS,9GS,10GS)Removal of the Battery of the Emergency Power-Supply UnitFlushing of the Principal Total Pressure LinesFlushing of the Principal Static Pressure LinesDraining and Flushing of Standby Pneumatic CircuitsDraining and Flushing of the Standby Static and Standby Total Pressure lines (ISIS) Inspection/Check of the Engine (4005KM) (GTCP 36-300)APU Power Plant Visual Inspection (APS 3200) Preservation / Storage / De-preservation of the Engine (GTCP 36-300)Preservation/Storage/Return to Service of APU (APS 3200)Preservation/Storage/Return to Service of APU (131-9(A))Opening of the Passenger/Crew DoorClosing of the Passenger/Crew DoorOpening of the Emergency Exit Doors from the Passenger Compartment -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------

 


52-22-00-410-001 Closing of the Emergency Exit Doors from the Passenger Compartment 52-30-00-860-001 Open the FWD or AFT Cargo-Compartment Door with the Yellow Electric Pump 52-30-00-860-002 Close the FWD or AFT Cargo-Compartment Door with the
 Yellow Electric Pump 52-30-00-860-006 Open the Bulk Cargo-Compartment Door 52-30-00-860-008 Close the Bulk Cargo-Compartment Door 53-59-00-210-001 Operational Check of Single Drain Pipe Aft of FR70
 from Outside 54-50-00-200-001 General Inspection of the Pylon Drain System 72-00-00-600-006 Preservation for a Period up to 30 Days. 72-00-00-600-007 Preservation for a Period of 30 to 365 Days. 72-00-00-600-025 Preservation for a Period up to 90 Days. 10-12-00-991-002 Fig. 201
 3. Job Set-up
__________

 Subtask 10-12-00-860-061
 A. General

 (1) This section gives the procedure for aircraft storage in standard weather conditions but:
 (a)
 If aircraft storage is in high wind conditions:

 -do a check of the aircraft stability (Ref. TASK 05-57-00-200-001)
 -moor the aircraft (Ref. TASK 10-20-00-556-001) if necessary.

 (b)
 If aircraft storage is in cold weather conditions:


 -do the cold weather maintenance procedures: (Ref. TASK 12-31-21-660-001), (Ref. TASK 12-31-24-660-001), (Ref. TASK 12-31-25-660-001), (Ref. TASK 12-31-27-660-001), (Ref. TASK 12-31-28-660-001), (Ref. TASK 12-31-31-660-001), (Ref. TASK 12-31-32-660-001), (Ref. TASK 12-31-35-660-001), (Ref. TASK 12-31-38-660-001), (Ref. TASK 12-31-49-660-001), (Ref. TASK 12-31-51-660-001), (Ref. TASK 12-31-52-660-001), (Ref. TASK 12-31-71-660-001).
 NOTE : In cold weather conditions, we recommend to put a fiber
____ material between the tires and the ground surface.
 EFF : ALL  10-12-00Page 233   May 01/05R   CES

 

 Subtask 10-12-00-615-055

 B. Cleaning of the Aircraft
 (1)
 If necessary, clean the aircraft externally (Ref. TASK 12-21-11-615-001).

 (2)
 If necessary, clean the aircraft internally:
 (Ref. TASK 12-21-12-100-002)
 (Ref. TASK 12-21-12-100-003)
 (Ref. TASK 12-21-12-100-004)
 (Ref. TASK 12-21-12-100-005)
 (Ref. TASK 12-21-12-100-006)
 
中国航空网 www.aero.cn