(2) Do the EIS stop procedure (Ref. AMM TASK 31-60-00-860-002).
「一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一1 EFF : ALL ∞∞24-21-00∞∞∞∞∞∞∞∞∞∞Page 288
Aug 01/05 CES (3) De-energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-862-002).
TASK 24-21-00-810-841
No Automatic Connection of the IDG 2 or Loss of the GEN 2
1. Possible Causes
_______________
- IDG (4000XU)
- GCU-2 (1XU2)
- wiring
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
AMM 24-21-51-000-040 Removal of the Integrated Drive Generator -IDG 1(2),(4000XU) AMM 24-21-51-400-040 Installation of the Integrated Drive Generator -IDG
1(2),(4000XU) AMM 24-22-34-000-001 Removal of the GCU-1(2) (1XU1, 1XU2) AMM 24-22-34-400-001 Installation of the GCU-1(2) (1XU1, 1XU2) AMM 24-41-00-740-002 Operational Test of the Ground power Control Unit
(GPCU) R AMM 24-41-00-740-002 Operational Check of GAPCU via CFDS AMM 24-41-00-861-002 Energize the Aircraft Electrical Circuits from Engine 1(2) AMM 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied
from the External Power
AMM 31-60-00-860-001 EIS Start Procedure
AMM 71-00-00-710-003 Engine Automatic Start
AMM 71-00-00-710-028 Engine Shutdown
ASM 24-21/01
3. Fault Confirmation
__________________
A. Test
(1) Not applicable
4. Fault Isolation
_______________
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399,
A. If the fault symptom is identified by the CFDS message CHECK GCU 2 PIN B14A, B14B IDG 2 PIN B1, B2 WIRING and the upper ECAM DU warning GEN 2 FAULT:
- do a check of the wiring between the GCU 2 pins B/14A, B/14B and the IDG 2 pins B/1 and B/2 (Ref. ASM 24-21/01).
「一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一1 EFF : ALL ∞∞24-21-00∞∞∞∞∞∞∞∞∞∞Page 290
Aug 01/05 CES
(1) If the wiring is not correct:
- repair it.
(2) If the wiring is correct:
- do a check of the resistance of the IDG 2 MPU coil between pin B/1 and pin B/2 (17.5 Ohms plus or minus 3.5 Ohms at 25.C).
(a) If the resistance is out of the specified limits:
- replace the IDG (4000XU) (Ref. AMM TASK 24-21-51-000-040) and (Ref. AMM TASK 24-21-51-400-040).
(b) If the resistance is in the specified limits:
- replace the GCU-2 (1XU2) (Ref. AMM TASK 24-22-34-000-001) and (Ref. AMM TASK 24-22-34-400-001).
NOTE : Do not remove the GCU 2 before you do the other steps of
____
the trouble shooting.
B. Do this operational test to make sure that the system operates correctly.
(1) Aircraft Maintenance Configuration
(a) Energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-861-002).
(b) Do the EIS start procedure (Upper ECAM DU and lower ECAM DU only) (Ref. AMM TASK 31-60-00-860-001).
(2) On the ELEC panel 35VU:
- push, release and push again the GEN 2 pushbutton switch (3XU2).
(3) Do the operational test of the GPCU (Ref. AMM TASK 24-41-00-740-002).
(4) Start the engine 2 (Ref. AMM TASK 71-00-00-710-003). R **ON A/C 401-499,
R A. If there is no connection of the IDG 2 after engine start:
R NOTE : After an automatic or manual disconnection of the IDG 2, do a GCU2
____ R reset at the first engine start. In this case, this trouble R shooting procedure is not applicable.
R (1) Replace the IDG (4000XU) (Ref. AMM TASK 24-21-51-000-040) and (Ref. R AMM TASK 24-21-51-400-040).
「一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一1 EFF : ALL ∞∞24-21-00∞∞∞∞∞∞∞∞∞∞Page 291
Aug 01/05 CES
R B. Do this operational test to make sure that the system operates correctly.
R (1) Aircraft Maintenance Configuration
R (a) Energize the aircraft electrical circuits
R (Ref. AMM TASK 24-41-00-861-002).
R (b) Do the EIS start procedure (Upper ECAM DU and lower ECAM DU only)