Subtask 27-84-62-912-057
E. Electrical Bonding Test
(1) For track 5 and 11, do the electrical bonding test (Ref. TASK 20-28-00-869-002).
5. Close-up
________ Subtask 27-84-62-410-051
A. Close Access
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Install the applicable actuators:
-
for tracks 5, 6, 8, 10 and 12 (Ref. TASK 27-84-49-400-001)
-
for tracks 7, 9 and 11 (Ref. TASK 27-84-49-400-002).
(3)
Install the applicable slat:
-
for tracks 5 and 6 (Ref. TASK 27-84-64-400-002)
-
for tracks 7 and 8 (Ref. TASK 27-84-65-400-002)
-
for tracks 9 and 10 (Ref. TASK 27-84-66-400-002)
-for tracks 11 and 12 (Ref. TASK 27-84-67-400-002). Subtask 27-84-62-865-055
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): 5CV, 7CV.
Subtask 27-84-62-942-051
C. Removal of Equipment
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Remove the safety barriers.
(3)
Remove the warning notice(s).
(4)
Remove the access platform(s).
(5)
Remove the ground support and maintenance equipment, the special and standard tools and all other items.
TRACK - SLAT 2, 3, 4, 5 - INSPECTION/CHECK
__________________________________________ TASK 27-84-62-200-001 Dimensional Check of the Slat-To-Track Attachment Fittings, Tracks 5 Thru 12 WARNING : PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU
_______ START A TASK ON OR NEAR:
-
THE FLIGHT CONTROLS
-
THE FLIGHT CONTROL SURFACES
-
THE LANDING GEAR AND THE RELATED DOORS
-COMPONENTS THAT MOVE. WARNING : MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING
_______ GEAR.
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific safety barriers No specific warning notice
B. Consumable Materials
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
Material No. 04-024 AIB AIMS 09-06-001 SYNTHETIC GREASE FOR FLAP & SLAT MECHANISM (Ref. 20-31-00)
1EFF : ALL 1 27-84-62Page 601 1 1 May 01/04R 1 1 1CES 1
C. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
27-84-62-000-001 Removal of the Slat Tracks 5 thru 12
27-84-62-400-001 Installation of the Slat Tracks 5 thru 12
27-84-64-000-001 Removal of the No. 2 Slat
27-84-64-400-002 Installation of the No. 2 Slat
27-84-65-000-001 Removal of the No. 3 Slat
27-84-65-400-002 Installation of the No. 3 Slat
27-84-66-000-001 Removal of the No. 4 Slat
27-84-66-400-002 Installation of the No. 4 Slat
27-84-67-000-001 Removal of the No. 5 Slat
27-84-67-400-002 Installation of the No. 5 Slat
**ON A/C 001-049, 051-061, 101-105, 201-203,
27-84-62-991-008 Fig. 601
R **ON A/C 062-099, 106-149, 151-199, 204-299, 301-399, 401-499,
27-84-62-991-008-A Fig. 601A
**ON A/C ALL
27-84-62-991-009 Fig. 602
27-84-62-991-010 Fig. 603
27-84-62-991-011 Fig. 604
27-84-62-991-012 Fig. 605
27-84-62-991-013 Fig. 606
**ON A/C 001-049, 051-061, 101-105, 201-203,
27-84-62-991-014 Fig. 607
R **ON A/C 062-099, 106-149, 151-199, 204-299, 301-399, 401-499,
27-84-62-991-014-A Fig. 607A -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
**ON A/C ALL
27-84-62-991-015 Fig. 608
3. Job Set-up
__________
Subtask 27-84-62-941-052
A. Safety Precautions
(1)