FAA parts shall establish and maintain a Quality System in conformance with
Federal Aviation Regulation FAR 21.
2) FAA FAR Part 145 (Repair Stations) – Suppliers of overhauled or repaired FAA
Supplier Quality Assurance Requirements
Rev. P, March 06, 2008
18
parts shall be a FAA FAR 145 approved repair station and shall maintain a
Quality System which complies with Federal Aviation Regulation FAR 145.
3) E-8C Modification Phase Parts – Suppliers manufacturing E-8C Modification
Phase Parts (MODS) shall be a Vought Aircraft Industries, Inc. approved Level 1
or 2 per Table 1.
ADDITIONAL QUALITY SYSTEM REQUIREMENTS
In addition to the Quality system requirements identified in Table 1, unless
otherwise specified, the following additional documents and appendices are
imposed on all Purchase Orders. These documents can found under the “Quality”
tab at the following URL: http://www.vought.com/suppliers/.
• SQR-002 – Supplier Advanced Quality Requirements; SQR-002 is applicable
when “Key Characteristics” have been identified on the engineering drawing,
specification or as part of the configuration requirements on the purchase order.
Approval to SQR-002 is required before a supplier can receive a formal
purchase order that involves Key Characteristics.
• SQR-003 – Nonconformance Reference Handbook for Suppliers; Applicable to
all purchase orders
• SQR-004 – Supplier Quality Requirements “Control and Use of Digital Product
Definition”; SQR-004 is applicable if part design and/or configuration is defined
via a released digital dataset (e.g., CATIA, UNIGRAPHICS, MEDs, IGES, etc.).
Approval to SQR-004 is required before a supplier can receive Digital Data from
Vought Aircraft Industries, Inc. This does not apply during the Request for
Proposal/Quote phase, however approval must be obtained prior to
acceptance of formal purchase order and release of engineering
• SQR-008 – Requirements for Supplier Fabricated Tooling; Applicable on all
tooling purchase orders
• SQR-009 – Quality Assurance Acceptance Sampling Requirements for
Suppliers; Applicable to all purchase orders where the supplier performs
sampling inspection unless a sampling plan is already defined in the governing
specifications..
• SQR-010 – Hardness and Conductivity Requirements.; Applicable to all
purchase orders for metallic parts (i.e., sheet metal and machined)
Note: For Global Hawk program (codes GH & GL) all aluminum fabricated parts
require 100% conductivity inspection after fabrication. Conductivity ranges shall
be per AMS 2658.
Supplier Quality Assurance Requirements
Rev. P, March 06, 2008
19
.
2.2 PRE-PRODUCTION REVIEW / CONFORMITY ASSESSMENT
Vought reserves the right to perform with the Supplier a review of Vought’s
purchase order and deliverable product(s) key/critical elements. Vought will
evaluate supplier quality processes and product compliance using the Vought
Conformity Assessment. The assessment will cover specific areas of the supplier’s
QA system; build package flow down, control of tooling, digital data and products
that Vought procures from the supplier. Subject review will be performed to the
extent necessary to verify mutual understanding of purchase order requirements,
and ensure that Supplier’s production planning activities address all applicable
key/critical elements.
2.3 SPECIAL PROCESS REQUIREMENTS
When special processes listed in Vought “Approved Special Processors List”
(ASPL) are required by drawing, specification, Purchase Order, or other media, the
Supplier shall ensure that the processing source for these requirements, including
those performed by the supplier, are listed on the Vought ASPL prior to any
processing of hardware.
As a prerequisite for Vought ASPL approval, Nadcap must accredit Special
Processors. Vought subscribes to Nadcap for the following process categories:
• Nondestructive Testing
• Heat Treating
• Material Testing Laboratories
• Chemical Processes
• Coatings
• Welding
• Non Conventional Machining & Surface Enhancement – Shot Peening
• Composites
Vought reserves the right to validate Nadcap compliance to any processes that are
unique to Vought or outside the scope of normal industry practice and/or Nadcap
general audit practice. This requirement also applies to the first-tier suppliers with
internal process capabilities. In addition, if the supplier utilizes any external special
process sources, this requirement must be flowed down to the processing sources.