For level 1 findings, immediate action shall be taken by DGCA to revoke, limit or suspend in whole or in part, depending upon the extent of the level 1 finding, the continuing airworthiness management organisation approval, until successful corrective action has been taken by the organisation.

2.
 For level 2 findings, DGCA shall grant a corrective action period appropriate to the nature of the finding that shall not be more than 30 days. In certain circumstances, at  the end of this first period, and subject to the nature of the finding DGCA Regional Office may extend the 30 day period by 15 days subject to a satisfactory corrective action plan. 


Rev 0, dated 2nd March, 2010  225
(b) Action shall be taken by DGCA to suspend in whole or part the approval in case of failure to comply within the timescale granted by DGCA. 
M.B.706 Changes
(a)  
DGCA shall comply with the applicable elements of the initial approval for any change to the organisation notified in accordance with point M.A.713.

(b)  
DGCA may prescribe the conditions under which the approved continuing airworthiness management organisation may operate during such changes unless it determines that the 


approval should be suspended due to the nature or the extent of the changes.
(c)  For any change to the continuing airworthiness management  exposition:
i.  In the case of direct approval of changes in accordance with M.A.704(b), DGCA shall verify that the procedures specified in the exposition are in compliance with CAR-M before formally notifying the approved organisation of the approval.
ii.  In the case an indirect approval procedure is used for the approval of the changes in accordance with point M.A.704(c), DGCA shall ensure (i) that the changes remain minor and (ii) that it has an adequate control over the approval of the changes to ensure they remain in compliance with the requirements of CAR-M. 
M.B.707 Revocation, suspension and limitation of an approval
 DGCA shall:
(a)
suspend  an approval on reasonable  grounds in the case of potential safety threat, or;

(b)
suspend, revoke or limit  an approval pursuant to M.B.705.


Rev 0, dated 2nd March, 2010
226
Rev 0, dated 2nd March, 2010
227
SUBPART H
CERTIFICATE OF RELEASE TO SERVICE — CRS
M.B.801 Certificate of Release to Service - CRS
DGCA shall:
(a)
ensure CRS has to be issued by the operator as required in M.A. 801.

(b)
ensure appropriate certifying staff used by the maintenance organisation.

(c)
ensure compliance of appropriate certification by the pilot – owner as required in M.A.             


803.
(d) ensure that the record keeping of the operator for issue of CRS is up to date and records are retained for the specified periods.
Rev 0, dated 2nd March, 2010
228
SUBPART I
AIRWORTHINESS REVIEW CERTIFICATE
M.B.901 Assessment of recommendations
Upon receipt of an application and associated airworthiness review certificate recommendation in accordance with M.A.901:
1.
Appropriate qualified personnel from DGCA shall verify that the compliance statement contained in the recommendation demonstrates that a complete M.A.710 airworthiness review has been carried out.

2.
DGCA shall investigate and may request further information to support the assessment of the recommendation. 


M.B.902 Airworthiness review by DGCA
(a). When DGCA carries out the airworthiness review and issues the airworthiness review certificate CA Form 15a (Appendix III), it shall carry out the airworthiness review in accordance with point M.A.710.
(b) DGCA shall have appropriate airworthiness review staff to carry out the airworthiness reviews.
 