R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 52-21-11Page 506 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1 TASK 52-21-11-820-002


 Adjustment of the Hatch Control Handle
 WARNING : MAKE SURE THAT THE SAFETY/LOCK PIN IS CORRECTLY INSTALLED IN THE
_______ REGULATOR VALVE ASSEMBLY OF THE INFLATION RESERVOIR. THIS PREVENTS ACCIDENTAL:
 -DISCHARGE OF THE INFLATION RESERVOIR
 -DEPLOYMENT OF THE ESCAPE-SLIDE
 WHICH CAN CAUSE INJURY AND/OR DAMAGE.

 WARNING : MAKE SURE THAT THE LATCH PIN IS RETRACTED IN THE DISARMED POSITION
_______ DURING THE REMOVAL AND INSTALLATION PROCEDURE. THIS PREVENTS AN ACCIDENTAL OPERATION OF THE ESCAPE SLIDE MECHANISM DURING THE REMOVAL/INSTALLATION.
 WARNING : MAKE SURE THAT THE SAFETY PIN IS CORRECTLY INSTALLED IN THE HATCH
_______ FRAME IF THE EMERGENCY EXIT HATCH IS REMOVED. THIS PREVENTS AN ACCIDENTAL OPERATION OF THE ESCAPE SLIDE MECHANISM DURING THE MAINTENANCE.
 1. Reason for the Job
__________________
 To adjust the hatch control handle of the locking mechanism.
 2. Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
98D52207539000 1 TOOL SET - EMERGENCY DOORS, ADJUSTMENT
 B. Consumable Materials
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
No specific  lockwire, corrosion-resistant steel, dia. 0.8 mm
 (0.032 in.)
 Material No. 05-027  USA MIL-L-81309 RUST INHIBITOR(FOR CORROSION USE 15-004) (Ref. 20-31-00)
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 52-21-11Page 507 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1


 C. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION
 -------------------------------------------------------------------------------
25-23-47-000-001 Removal of the Lining from the Emergency Exit Hatches 25-23-47-400-001 Installation of the Lining on the Emergency Exit
 Hatches
 52-21-11-000-001 Removal of the Emergency Exit Hatch
 52-21-11-000-002 Removal of the Hatch Locking Mechanism
 52-21-11-400-001 Installation of the Emergency Exit Hatch
 52-21-11-400-002 Installation of the Hatch Locking Mechanism
 52-21-11-991-006 Fig. 501

 **ON A/C 001-049, 051-099, 101-149, 201-299,
 52-21-11-991-007 Fig. 502
R **ON A/C 151-199, 401-499,
 52-21-11-991-007-A Fig. 502A
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
 3. Job Set-up
__________
 Subtask 52-21-11-010-057
 A. Get Access
 (1)
 Remove the emergency exit hatch (Ref. TASK 52-21-11-000-001).

 (2)
 Remove the hatch lining from the hatch structure (Ref. TASK 25-23-47-000-001).

 (3)
 If necessary, carefully remove the insulation packs from the work area.


R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 52-21-11Page 508 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1


 4. Procedure
_________
 **ON A/C 001-049, 051-099, 101-149, 201-299,

 (Ref. Fig. 502/TASK 52-21-11-991-007) R **ON A/C 151-199, 401-499,
 (Ref. Fig. 502A/TASK 52-21-11-991-007-A) R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
 Subtask 52-21-11-820-051
 A. Adjustment of the Hatch Control Handle
 (1)
 Remove the connection rod (22) from the locking hook (21) and the pull lever (29) (Ref. TASK 52-21-11-000-002).

 (2)
 Remove the spring (23) from the pull lever (29). NOTE : This is only necessary on the side of the connection rod (22).

____

 (3)
 Remove the cotter pin (26), the washer (27) and the pivot pin (28) from the pull lever (29). Discard the cotter pin (26).

 (4)
 Install the TOOL SET - EMERGENCY DOORS, ADJUSTMENT (98D52207539000) between the locking hook (21) and the pull lever (29) as follows:

 (a)
 Attach the dead point gage with the rigging pin to the pull lever (29).

 (b)
 Attach the dead point gage with the pip-pin to the locking hook (21).

 

 (5)
 Release the jam nuts (24) to move the adjustment screws (25).

 (6)
 Turn the adjustment screws (25) until the adjustment pin of the TOOL SET - EMERGENCY DOORS, ADJUSTMENT can engage in the hole of the pull lever (29).
 