A. De-energize the ground service network
 (Ref. TASK 24-42-00-862-001)
1EFF : ALL 1 23-73-22Page 411 1 1 Aug 01/05 1 1 1CES 1 DIRECTOR - CIDS (101RH,102RH) - REMOVAL/INSTALLATION
____________________________________________________
 TASK 23-73-34-000-001
 Removal of the CIDS Director (101RH,102RH)
 1.
 Reason for the Job
__________________
 Self Explanatory
 2.
 Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
 -------------------------------------------------------------------------------
No specific blanking caps
 No specific circuit breaker(s) safety clip(s)
 No specific access platform 1.6 m (5 ft. 3 in.)
 B. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION
 -------------------------------------------------------------------------------
52-41-00-010-002 Open the Avionics Compartment Doors for Access
 23-73-34-991-001 Fig. 401
 3. Job Set-up
__________
 Subtask 23-73-34-010-050
 A. Get Access
 (1) Put the access platform in position at zone 128. R (2) Open the access door 824 (Ref. TASK 52-41-00-010-002).
 1EFF : ALL 1 23-73-34Page 401 1 1 Feb 01/02 1 1 1CES 1 1EFF : ALL 1 23-73-34Page 402 1 1 Aug 01/05 1 1 1CES 1
 Subtask 23-73-34-865-050 B. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------FOR 101RH **ON A/C 001-049, 051-099, 101-105, 201-299, 
R  49VU COM/CIDS/DIR 1 AND 2/ESS **ON A/C 106-149, 301-399, 401-499, 150RH  G02  
R  49VU AIR COND/CIDS/SDF/DIR1 ESS **ON A/C 106-149, 151-199, 301-399, 401-499, 15WH  C05  
49VU COM DIR ESS/1 **ON A/C 001-049, 051-099, 101-105, 151-199, 201-299, 150RH  G01 
 121VU COM NAV/CIDS/DIR 1 AND 2/NORM **ON A/C 301-399, 151RH  M05 
R  121VU COM NAV/CIDS/DIR NORM/1 **ON A/C 106-149, 301-399, 401-499, 151RH  M06  
122VU AIR COND/CIDS/SDF/DIR NORM/1 **ON A/C ALL 17WH  T17 
 FOR 102RH
 -------------------------------------------------------------------------------
PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------**ON A/C 001-049, 051-099, 101-105, 201-299, 
R  49VU COM/CIDS/DIR 1 AND 2/ESS **ON A/C 106-149, 301-399, 401-499, 150RH  G02  
R  49VU AIR COND/CIDS/SDF/DIR2 ESS **ON A/C 106-149, 401-499, 18WH  C06  
R  49VU COM/CIDS/DIR ESS/2 **ON A/C 106-149, 151-199, 301-399, 401-499, 157RH  G02  
49VU COM DIR ESS/1 **ON A/C 151-199, 301-399, 150RH  G01 
 49VU COM DIR ESS/2 **ON A/C 001-049, 051-099, 101-105, 151-199, 201-299, 157RH  G02 
R  121VU COM NAV/CIDS/DIR 1 AND 2/NORM **ON A/C 106-149, 151-199, 401-499, 151RH  M05  
121VU COM NAV/CIDS/DIR NORM/2 **ON A/C 301-399, 156RH  M06 
 121VU COM NAV/CIDS/DIR NORM/2 121VU COM NAV/CIDS/DIR NORM/1  156RH 151RH  M07M06
1EFF : ALL 1 23-73-34Page 403 1 1 Aug 01/05 1 1 1CES 1
 -------------------------------------------------------------------------------
PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------R **ON A/C 106-149, 301-399, 401-499,
 122VU AIR COND/CIDS/SDF/DIR NORM/2 14WH T18 **ON A/C ALL
 4. Procedure
_________
 (Ref. Fig. 401/TASK 23-73-34-991-001)
 Subtask 23-73-34-020-050
 A. Removal of the CIDS Director
 (1)
 Loosen the nuts (3).
 (2)
 Lower the nuts (3).
 (3)
 Pull the CIDS director (5) on its rack (2) to disconnect the electrical connectors (1).
 (4)
 Remove the CIDS director (5) from its rack (2).
 (5)
 Put blanking caps on the disconnected electrical connectors (1).
 1EFF : ALL 1 23-73-34Page 404 1 1 Aug 01/05 1 1 1CES 1
 CIDS Director Figure 401/TASK 23-73-34-991-001 
 1EFF : 1 1R 1CES  ALL  1 11 1 23-73-34 Page 405 May 01/05
 TASK 23-73-34-400-001 
 Installation of the CIDS Director (101RH,102RH) 
 1. Reason for the Job__________________ 
 Self Explanatory 
 