25-51-05
ú ú 02 Page 403 ú May 28/99
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
757
MAINTENANCE MANUAL
B. References
(1)
AMM 24-22-00/201, Electrical Power - Control
(2)
AMM 25-51-00/201, Cargo Loader Systems
(3)
AMM 25-51-00/501, Cargo Loader System
(4)
AMM 25-51-03/401, Forward Cargo Loader Rollers
C. Access
(1)
Location Zones
121 Forward cargo compartment (Left)
122 Forward cargo compartment (Right)
(2)
Access Panels
821 No. 1 cargo door
D. Procedure
S 824-016
(1)
Put the aft bulkhead and module 3 at the aft end of the cargo compartment.
S 434-017
(2)
Connect the aft bulkhead to module 3:
(a)
Install the bolts in the sidewall. Do not tighten the bolts.
(b)
Install the screws in the base. Do not tighten the screws.
(c)
Align the bulkhead and the walls on module 3. Tighten the screws and the bolts.
S 434-018
(3)
Install the aft track rollers on the base of module 3 (AMM 25-51-03/401). Make sure the cam follower points to the side restraint part of the roller track.
S 434-019
(4)
Install the retainer on the aft end of the base of module 3.
S 434-020
(5)
Install the aft upper rollers on module 3 (AMM 25-51-03/401). Install the adjustment spacers under the rollers if it is necessary.
(6)
Put module 2 in position in the cargo compartment.
S 984-021
EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. AIRPLANES WITH FORWARD CARGO LOADER ú
25-51-05
ú ú 02 Page 404 ú May 28/99
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
757
MAINTENANCE MANUAL
(7) S 434-022Install the aft upper rollers on module 2 (AMM 25-51-03/401). Install the adjustment spacers under the rollers if it is necessary.
(8) S 984-038Lift the forward edge of module 3. Move module 2 under module 3 (approximately 3 inches), then lower module 3 on module 2.
(9) S 824-023Move modules 2 and 3 to the aft end of the cargo compartment.
S 984-024
(10)
Put module 1 in the cargo compartment, forward of modules 2 and 3.
S 434-025
(11)
Install the stops on the aft end of the base of module 1.
S 434-026
(12)
Install the forward and aft upper rollers on module 1 (AMM 25-51-03/401). Install the adjustment spacers under the rollers if it is necessary.
S 714-027
(13)
Push the plunger found at the aft end of the base of module 1. Make sure the plunger touches the floor restraint by 0.10-0.15 inch. Adjust the floor restraint, if it is necessary.
S 984-028
(14)
Lift the forward edge of module 2. Move module 1 under module 2 (approximately 3 inches), then lower module 2 on module 1.
S 434-029
(15)
Install the forward upper rollers on module 3 (AMM 25-51-03/401).
S 434-030
(16)
Install the forward upper rollers on module 2 (AMM 25-51-03/401).
S 014-031
(17)
Open the access door on the rear bulkhead of module 3.
S 434-032
(18)
Install the ball lock pins to connect module 3 to the drive screw.
S 414-033
(19)
Close the access door.
S 864-034
(20)
Remove DO-NOT-CLOSE tag and close this P34 panel circuit breaker: