 F. Power-up Tests Initialization and Cockpit Repercussions
 (1)
 Conditions of power-up tests initialization

 -How long the computer must be de-energized: 1 s.
 -A/C configuration:
 -whatever the A/C configuration on ground

 (2)
 Progress of power-up tests

 -Duration: 20 s.
 -Cockpit repercussions directly linked to power-up test accomplishment (some other repercussions may occur depending on the A/C configuration but these can be disregarded):
 -none

 (3)
 Results of power-up tests (cockpit repercussions, if any, in case of tests pass/tests failed).

 -
Tests pass:

 -none

 -
Tests failed:

 


 -GPWS panel:
 FAULT legend of SYS P/BSW on

 -MASTER CAUT light on and single chime
 -
ECAM warning:
 NAV GPWS FAULT


 -
ECAM STATUS:
 GPWS INOP

 

R 1EFF : 001-049, 051-060, 101-104, 1 34-48-00Page 45 1 1 Config-2 May 01/05 1 1 1CES 1


 Maintenance Test Procedure - Sub-Menu Function 1/3
 Figure 015

R 1EFF : 001-049, 051-060, 101-104, 1 34-48-00Page 46 1 1 Config-2 May 01/05 1 1 1CES 1


 Maintenance Test Procedure - Sub-Menu Function 2/3
 Figure 016

R 1EFF : 001-049, 051-060, 101-104, 1 34-48-00Page 47 1 1 Config-2 May 01/05 1 1 1CES 1


 Maintenance Test Procedure - Sub-Menu Function 3/3
 Figure 017

 1EFF : 001-049, 051-060, 101-104, 1 34-48-00Page 48 1 1 Config-2 May 01/05 1 1 1CES 1


 GROUND PROXIMITY WARNING SYSTEM (GPWS) - SERVICING
__________________________________________________
 TASK 34-48-00-610-001
 Uploading of the Enhanced GPWC Database

 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 1.6 m (5 ft. 3 in.)
 B. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied
 from the External Power 34-48-00-740-002 BITE Test of the Enhanced GPWC 52-41-00-410-002 Close the Avionics Compartment Doors after Access
 **ON A/C ALL
R Post SB 34-1189 For A/C 001-049,051-060,101-104,
 34-48-00-991-002 Fig. 301
 **ON A/C ALL
 3. Job Set-up
__________
 NOTE : Refer th the equipment manufacturer Service Bulletin related to the

____
 version of the database that you upload.

 1EFF : ALL 1 34-48-00Page 301 1 1 May 01/05 1 1 1CES 1 **ON A/C ALL


R  Post SB 34-1189 For A/C 001-049,051-060,101-104, Subtask 34-48-00-861-055
 A. Energize the aircraft electrical circuits
 (Ref. TASK 24-41-00-861-002).

 Subtask 34-48-00-010-053
 B. Get Access
 (1) Put the access platform in position at the access door 824 in zone
 128.
 (2) Open the access door 824.
 Subtask 34-48-00-865-066

 C. Make sure that this(these) circuit breaker(s) is(are) closed:
 -------------------------------------------------------------------------------
PANEL DESIGNATION  IDENT. LOCATION
 -------------------------------------------------------------------------------
121VU EIS/GPWS/115VAC  3WZ P07
 **ON A/C ALL
 4. Procedure
_________ **ON A/C ALL R Post SB 34-1189 For A/C 001-049,051-060,101-104, (Ref. Fig. 301/TASK 34-48-00-991-002) Subtask 34-48-00-970-050
 A. Loading of the PCMCIA Card Software NOTE : Before you load the software make sure that the version of the
____
 terrain data base is correct.

 (1) Make sure that the COMPUTER OK LED on the face of the Enhanced GPWC, is on.
 1EFF : ALL 1 34-48-00Page 302 1 1 May 01/05 1 1 1CES 1


 Enhanced GPWC Face Figure 301/TASK 34-48-00-991-002 
R 1EFF : 1 1 1CES  ALL  1 111 34-48-00 Page 303 Aug 01/00

 

 (2)
 Open the door on the face of the Enhanced GPWC.

 (3)
 Put the PCMCIA card into the PCMCIA card slot.
 