时间:2011-02-24 09:37来源:蓝天飞行翻译 作者:admin
曝光台 注意防骗 网曝天猫店富美金盛家居专营店坑蒙拐骗欺诈消费者

 (6)
 Remove the blanking plug from the air outlet.

 (7)
 Remove the blanking caps from the electrical connectors.

 (8)
 Make sure that the electrical connectors are clean and in the correct condition.


 (9) Connect the electrical connector (5).
 Subtask 21-26-53-865-052

 B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): 6HQ
 Subtask 21-26-53-710-050
 C. Do an operational test of the ventilation system of the avionics equipment (Ref. TASK 21-26-00-710-001).
 NOTE : As an alternative procedure, you can do this operational test
____
 without the CFDS (Ref. TASK 21-26-00-710-001).

R 1EFF : ALL 1 21-26-53Page 410 1 1 Feb 01/05 1 1 1CES 1


 5. Close-up
________ Subtask 21-26-53-942-050
 A. Close Access
 (1) Make sure that the work area is clean and clear of tool(s) and other items.
 (2) Remove the access platform(s). Subtask 21-26-53-862-051
 B. De-energize the ground service network
 (Ref. TASK 24-42-00-862-001).

R 1EFF : ALL 1 21-26-53Page 411 1 1 Feb 01/05 1 1 1CES 1 VALVE - CONDITIONED AIR INLET (21HQ) - REMOVAL/INSTALLATION


___________________________________________________________
 TASK 21-26-54-000-001
 Removal of the Conditioned Air Inlet Valve (21HQ)
 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------
REFERENCE  QTY DESIGNATION
 -------------------------------------------------------------------------------
R  No specific blanking caps
R  No specific blanking plugs No specific circuit breaker(s) safety clip(s) No specific access platform 1.6 m (5 ft. 3 in.)
 B. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE  DESIGNATION
 -------------------------------------------------------------------------------
24-42-00-861-001  Energize the Ground Service Network from the External Power R 21-26-54-991-001 Fig. 401
 3. Job Set-up
__________
 CAUTION : USE ONLY THE GROUND SERVICE NETWORK TO SUPPLY ELECTRICITY BECAUSE

_______ THE AVIONICS VENTILATION SYSTEM IS NOT SERVICEABLE. IF YOU ENERGIZE THE AIRCRAFT ELECTRICAL CIRCUITS WITHOUT THE VENTILATION SYSTEM YOU WILL CAUSE DAMAGE TO ELECTRICAL EQUIPMENT.
 Subtask 21-26-54-861-050
 A. Energize the ground service network
 (Ref. TASK 24-42-00-861-001).

 

 Subtask 21-26-54-865-050
 B. Open, safety and tag this(these) circuit breaker(s):
 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------49VU AIR COND/AVNCS VENT/CTL 6HQ D06 49VU AIR COND/AVNCS VENT/CTL 5HQ D05 122VU AIR COND/AVNCS/VENT/MONG 3HQ Y17
 Subtask 21-26-54-010-050
 C. Get Access
 (1)
 Put the access platform in position at the access door 824.

 (2)
 Open the access door 824.


 4. Procedure
_________ (Ref. Fig. 401/TASK 21-26-54-991-001) R **ON A/C 001-049, 053-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 Subtask 21-26-54-020-050
 A. Removal of the Conditioned Air Inlet Valve
 (1)
 Disconnect the electrical connector (5) from the valve (6).

 (2)
 Put blanking caps on the disconnected electrical connectors.

 (3)
 Remove the clamps (4) and (2). NOTE : Do not discard the clamps (4) and (2). You must keep and use

____ them during the installation procedure.

 (4)
 Move the flexible sleeve (3) on the pipe (1) to release the valve (6).

 (5)
 Remove the clamp (8) and remove the valve (6).

 (6)
 Remove and discard the O-ring (7).

 (7)
 Remove the flexible sleeve (3).

 


 Conditioned Air Inlet Valve Figure 401/TASK 21-26-54-991-001
 1EFF : 1 1R 1CES  ALL  1 11 1 21-26-54 Page 403 May 01/01

 

 (8) Put blanking plugs on the disconnected line ends. 
R  **ON A/C 051-052, 
R  Subtask 21-26-54-020-050-A 
R  A. Removal of the Conditioned Air Inlet Valve 
R  (1) Disconnect the electrical connector (5) from the valve (6). 
 