 21-51-41-400-001  Installation of the Ozone Filter 100HM (101HM)
 21-51-51-000-001  Removal of the Pack Flow-Control Valve
 21-51-51-000-001  Removal of the Pack Flow-Control Unit
 21-51-51-400-001  Installation of the Pack Flow-Control Valve
 21-51-51-400-001  Installation of the Pack Flow-Control Unit
 21-52-16-000-001  Removal of the Water Extractor 10HM8 (11HM8)
 21-52-16-400-001  Installation of the Water Extractor 10HM8 (11HM8)
 21-52-21-000-001  Removal of the Air Cycle Machine 10HM1 (11HM1)
 21-52-21-400-001  Installation of the Air Cycle Machine 10HM1 (11HM1)
 21-52-32-400-001  Installation of the Condenser 10HM2 (11HM2)
 21-52-42-000-001  Removal of the Water Injector 20HM (21HM)
 21-52-42-400-001  Installation of the Water Injector 20HM (21HM)
 21-52-43-400-001  Installation of the Pack Downstream Check-Valves 15HM
 and 16HM
 21-63-00-710-004  Operational Test of the Cockpit and Cabin Temperature
 Control with CFDS/MCDU

 1EFF : ALL 1 21-00-00Page 267 1 1 Aug 01/05R 1 1 1CES 1


 -------------------------------------------------------------------------------
REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-861-002
24-41-00-862-002
31-60-00-860-001 31-60-00-860-002 36-11-49-000-042 36-11-49-400-042 36-12-41-000-001 36-12-41-400-001 49-00-00-860-003 49-00-00-860-004 49-00-00-860-005 49-00-00-860-006 49-00-00-860-008 49-00-00-860-009 53-35-13-000-002
53-35-13-400-002
71-00-00-710-003 71-00-00-710-028 ACMM 211104
 CMM  214302
 CMM  214352
 CMM  215102
 CMM  215110
 CMM  215202
 CMM  215204
 CMM  215234

 21-00-00-991-004 __________
3. Job Set-up
 Subtask 21-00-00-941-052Energize the Aircraft Electrical Circuits from the External PowerDe-energize the Aircraft Electrical Circuits Supplied from the External PowerEIS Start ProcedureEIS Stop ProcedureRemoval of the Pylon Interface DuctInstallation of the Pylon Interface DuctRemoval of a Bleed-Air DuctInstallation of a Bleed-Air DuctAPU Start by External Power (GTCP 36-300)APU Shutdown by External Power (GTCP 36-300)APU Start by External Power (APS 3200)APU Shutdown by External Power (APS 3200)APU Start by External Power (131-9(A))APU Shutdown by External Power (131-9(A))Removal of the Quick-Release Access Panels from the Belly Fairing StructureInstallation of the Quick-Release Access Panels on the Belly Fairing StructureEngine Automatic StartEngine Shutdown
Fig. 201
 A. Necessary Special Tools
 (1) Special blanking caps - locally manufactured - see Job Set-up 2 off. Manufactured with reference to (Ref. Fig. 201/TASK 21-00-00-991-004) and to SIL 21-029.
 1EFF : ALL 1 21-00-00Page 268 1 1 Aug 01/05R 1 1 1CES 1


 (2) Warm air blower (commercial hair dryer). NOTE : A commercial hair drier could be used as the warm air blower.
____
 Subtask 21-00-00-861-052

 B. Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-002). Subtask 21-00-00-860-067
 C. Aircraft Maintenance Configuration
 (1)
 Do the EIS start procedure (Ref. TASK 31-60-00-860-001).

 (2)
 On the ECAM control panel push the COND pushbutton switch.

 (3)
 Make sure that the CKPT, the FWD cabin and the AFT cabin temperatures shown on the ECAM lower display unit (DU) are below 24 deg. C.

 (4)
 If one or more of the temperatures is more than 24 deg. C you must:

 (a)
 Lower the temperature (Ref. TASK 12-33-21-618-001) or,

 (b)
 Do the alternative ECS decontamination procedure (Ref. TASK 21-00-00-615-004).

 


 Subtask 21-00-00-865-070
 D. Open, safety and tag this(these) circuit breaker(s):
 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------49VU AIR BLEED/ENG 1/MONG 2HA1 D11

R **ON A/C 401-499,
 49VU AIR COND/TEMP CTL/SYS 1 CHAN B/28VDC 52HH D08 R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399,
 122VU AIR COND/ZONE TEMP CTL/28VDC/SYS2 4HK V20 122VU AIR COND/ZONE TEMP CTL/28VDC/SYS1 3HK V19 122VU AIR COND/ZONE TEMP CTL/115VAC/SYS2 2HK V18 122VU AIR COND/ZONE TEMP CTL/115VAC/SYS1 1HK V17
R 1EFF : ALL 1 21-00-00Page 269 1 1 Aug 01/05 1 1 1CES 1


 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION
 