• 热门标签

当前位置: 主页 > 航空资料 > 机务资料 >

时间:2011-05-24 14:58来源:蓝天飞行翻译 作者:航空
曝光台 注意防骗 网曝天猫店富美金盛家居专营店坑蒙拐骗欺诈消费者

(7)  Measure the radial play of each main bolt in the related spar stub bush.  Maximum radial play 0.2 mm (0.008 in). 
(8)  Lubricate these items: S Main bolts. S Front and rear main bulkhead bushes. S Spar bushes. S A and B-bolt bushes in the end ribs. S A and B-bolts in the wing root ribs.  Refer to Section 12-20. 

57-10-00
AMM

Detail Steps/Work Items  Key Items/References 
(9)  Examine the flap torsion tube and transfer lever in the center section. Look specially for damage to the transfer pins. 
(10)  Examine the flap. Look specially for damage to the inner end rib. 

57-10-00
Wings
AMM

D. Install the Wings
Use this procedure to install the left wing or the right wing. Where a part of the procedure applies to only one wing it will tell you so.
Detail Steps/Work Items  Key Items/References 
(1)  Do the pre-installation check.  Refer to Paragraph C. 
WARNING: USE 3 PERSONS TO LIFT THE WING. IF YOU DO NOT, YOU CAN CAUSE INJURY. CAUTION: DO NOT LIFT ON THE FLAP. YOU CAN DAMAGE THE FLAP. CAUTION: DO NOT LET THE SPAR STUBS TOUCH THE CENTER SECTION SHELLS. YOU CAN DAMAGE THE SHELLS. 
Note: Until you install the main bolts, one person must lift the wing tip. One person must lift the leading edge at the root rib. One person must lift the trailing edge at the root rib. 
(2)  Lift the wing into position: S Move the spar stubs part way into the front and rear main bulkheads. S Put the electrical cable, Pitot, static and stall warning tubes through the conduit in the leading edge of the center section. S Align the flap inner rib with the transfer pins on the transfer lever. S Move the wing fully into the center section to engage the A and B-bolts and the flap transfer pins.  Hold the wing in position. Hold the wing in position. Hold the wing in position. 
(3)  Install the main bolts: S Hold the weight of the wing. S Install each bolt.  If necessary, move the wing tip a small amount up and down to help install the main bolts. 

Doc # 6.02.01 Page 209
Rev. 4 09 Jan 2003

57-10-00
AMM

%
%

%
%
%

%
%
%

DA 40 Series

Detail Steps/Work Items  Key Items/References 
(4)  Install the locking tubes on the inboard and outboard main bolts: S Install the long end piece in one main bolt. S Move the tube over the long end piece. S Install the short end piece in the other main bolt. S Move the tube over the short end piece. S Install the bolt, washer and self-locking nut through the tube and the long end piece.  Refer to Figure 3. 
(5)  Connect these items under the left pilot’s seat: S The Pitot hose. S The static hose. S The stall warning hose.  For left wing only. The hose is 8 mm (5/16 in) diameter. (Green color). The hose is 8 mm (5/16 in) diameter. (Purple color). The hose is 10 mm (3/8 in) diameter. (Transparent). 
(6)  Connect the electrical connector in the wing harness.  Left wing: connector P2400, under the pilot's seat. Right wing: connector P2401, under the co-pilot's seat. 
(7)  Connect the fuel hose(s) in the stub-wing. 
(8)  Connect the flap push-rod: S Install the bolt, washer and self-locking nut.  Through the center section rear panel. Torque: 6.4 Nm (4.7 ft.lb). 
(9)  Connect the aileron push-rod: S Install the bolt, washer and self-locking nut.  Through the center section rear panel. Torque: 6.4 Nm (4.7 ft.lb). 
(10)  If you must also install the other wing, do items 1 to 9 again for that wing. 
(11)  Connect the battery.  Refer to Section 24-31 (Lycoming version) or 24-34 (TAE version). 
(12)  Do a test for correct operation and range of movement of the flap system. If necessary, adjust the flap system.  Refer to Section 27-50. 
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:钻石40飞机维护手册 DA 40 SERIES AMM 4(68)