comply with the airworthiness
requirements of TGL 10 and
AC 90-100
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 7 Implementing RNP, October 4-5 2005
RNAV in Terminal Area
The radio navaid infrastructure supports the required
Navigation Accuracy level
– It is not the Operator’s duty to verify the adequacy of radio navaid
coverage
– Inadequate radio navaid coverage should be notified by NOTAM or
on the instrument procedure chart ⇒ GPS required
GPS acceptable if TSO C 129A certified
– All Airbus with GPS comply
Single or Dual RNAV system
– Single system acceptable, unless flight path below area MSA
or/and (?) no radar coverage (TGL 10)
– Should be stated on the instrument procedure chart
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 8 Implementing RNP, October 4-5 2005
RNAV in Terminal Area
Operational Approval:
Aircraft capability
– Stated in the AFM
Crew documentation
– OPS Manual based on FCOM
– MEL
Crew training
– RNAV system knowledge
– Briefing on RNP RNAV
Navigation database integrity
– Approved database suppliers
– Operator’s validation
Navigation Database
validation was the main
challenge to deploy P-RNAV.
The main database providers
are now ED76/D0200A
compliant
RNAV in approach
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 10 Implementing RNP, October 4-5 2005
RNAV in approach
RNAV (GNSS) “Sensor related”
RNP RNAV “Performance related”
– RNP 0.3,
– Straight final segment
DA as low as 250 ft AGL
with FINAL APP mode
(LNAV/VNAV ) guidance
A large part of the Airbus world fleets can
fly instrument approach procedures
published under ICAO PANS OPS (or
TERPS) criteria.
A lot of destinations could benefit from the
implementation of such procedures.
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 11 Implementing RNP, October 4-5 2005
The Advantages of RNAV Approaches
[RW27]
[RW27]
-3°
FACF FAF
IF TF TF
DA
MAP]
MAP]
CF CF
MDA
SDF
• Approach on runway axis
• Final descent at a constant Flight Path Angle to a DA
• Stabilized approach leading 50 ft above runway threshold
• Accuracy of navigation
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 12 Implementing RNP, October 4-5 2005
[RW27]
[RW27]
-3°
FACF FAF
IF TF TF
• All Airbus with an FMS and
GPS are capable to fly such
RNAV Approaches
The Advantages of RNAV Approaches
• All Airbus with FMS 2 can
fly in addition RF legs
Since mid-80’s, Airbus
promotes a constant slope
NPA rather than step-down
(“dive and drive”) procedures
This is in line with the CDFA
concept (NPA OPS-41)
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 13 Implementing RNP, October 4-5 2005
RNAV in Approach - Operational Approval
Generic Approval for RNP 0.3 RNAV or RNAV(GNSS)
(PANS OPS)
Crew Procedures
– FCOM SOP
Dispatch Requirements
Crew Training
– Briefing on RNP RNAV
– Navigation system knowledge (known by all Airbus pilots)
– Use of RNAV navigation system (known by all Airbus pilots)
Training on FINAL APP mode
Documentation update
Navigation Database Integrity
Navigation Database
validation by the Operators
must be clarified by EASA
AMC 20 XZ
© AIRBUS 2005 S.A.S. All rights reserved. Confidential and proprietary document.
Airbus RNP Operations 14 Implementing RNP, October 4-5 2005
RNAV in Approach
It is now time to take benefit of Airbus aircraft
RNAV capabilities in approach
“PANS OPS” straight in RNP 0.3 RNAV or RNAV(GNSS)
approaches can easily be implemented:
Deletion of circling procedures
Deletion of “old style” NPAs
Access to new destinations