123
13.5.2 Training objective
13.5.2.1 This session provides generic objectives for training of engineering/installation ATSEP. This
training programme will be developed, implemented and delivered in compliance with ATSEP job functions.
13.5.2.2 The students shall perform their duties in accordance with approved standards and procedures.
Condition: 􀂃 In a laboratory environment, given exposure to specific systems/equipment along
with the appropriate and pertinent training material, reference documentation and
tools.
􀂃 Alternatively, use of simulation or scenario to enable the performance of the
objective without the need of the real equipment.
􀂃 Given a description of a specific system installation.
Performance: On a given situation, the engineering/installation ATSEP shall be able to:
􀂃 demonstrate installation dexterity;
􀂃 design installation drawings;
􀂃 apply the TRM skills;
􀂃 perform on-the-job duties.
Standard of 􀂃 All the descriptions should include the essential points of the given situation;
Accomplishment: 􀂃 All work should be performed as per the approved standards and procedures.
13.5.3 The typical training package for engineering/installation ATSEP
a) With references, the participant will describe the functions in ANSP operations and responsibilities:
􀂃 describe the relationship between the ANSP and the regulator;
􀂃 describe the purpose of the regulations;
􀂃 describe the importance of engineering standards and procedures;
􀂃 describe the life cycle management principles;
􀂃 describe ATM and CNS specialties;
􀂃 describe design and implementation specialties;
􀂃 describe the various phases of an installation project.
b) With references, the participant will prepare for installation activities:
􀂃 describe ESD and safety standards;
􀂃 explain the drawing system;
􀂃 gather installation documents;
􀂃 interpret documentation;
􀂃 procure installation materials;
􀂃 describe how to configure installation items.
c) With references, the participant will assemble PCBs and panels:
􀂃 assemble PCBs;
􀂃 fabricate panels and interface panels;
􀂃 assemble panels.
d) With references, the participant will prepare power and ground cables:
􀂃 describe power systems and cables;
􀂃 assemble power cords for equipment racks;
􀂃 assemble ground cables;
Advance first edition (unedited) version – 30 August 2009
124
􀂃 prepare exothermic welded ground connection (outdoor demonstration).
e) With references, the participant will prepare RF cables and components:
􀂃 describe RF cables and systems;
􀂃 prepare RF cables for testing and installation;
􀂃 prepare tuned resonant cavities for installation;
􀂃 describe how to prepare RF cable to specified electrical length.
f) With references, the participant will terminate control cables:
􀂃 describe control cables and systems;
􀂃 terminate 25 pair control cables with Amp and TRW;
􀂃 terminate 25 pair control cables with BIX;
􀂃 terminate ribbon cables;
􀂃 terminate Cat 5 cables;
􀂃 terminate fiber optic cables;
􀂃 terminate cross connect wiring using wire wrap;
􀂃 Verify control cable connections.
g) With references, the participant will prefabricate racks:
􀂃 plan equipment rack;
􀂃 assemble rack;
􀂃 install equipment into rack (mechanical assembly);
􀂃 install equipment cables into racks (electrical assembly).
h) With references, the participant will install cross connections:
􀂃 plan cross connections;
􀂃 install cross connect wiring.
i) With references, the participant will describe the workshop to site transition processes:
􀂃 describe the pre-POP tests;
􀂃 describe the implementation review process;
􀂃 prepare equipment and/or shelter for shipping.
j) With references, the participant will install equipment racks:
􀂃 install racks into shelter;
􀂃 install ladder tray and conduits.
k) With references, the participant will install system interconnects and interfaces:
􀂃 install power and ground systems;
􀂃 install interconnect wiring;
􀂃 install RF system;
 