R 1EFF : 051-099, 106-149, 201-299, 301-399, 1 23-33-47Page 414 1 1 May 01/05 1 1 1CES 1 **ON A/C 301-399,
(Ref. Fig. 401B/TASK 23-33-47-991-001-B) R **ON A/C 051-099, 106-149, 201-299, 301-399,
Subtask 23-33-47-210-050
A. Make sure that the parts retained from the removed component are clean and in the correct condition.
R **ON A/C 051-099, 201-210,
Subtask 23-33-47-420-050
B. Installation of the Wall Disconnect Box (WBD).
(1)
Make sure that the electrical connectors are clean and in the correct condition.
FOR 50MK5
(2)
Remove the blanking caps from the termination plug (3) and the WDB connector J1.
(3)
Carefully install the termination plug (3) to the WDB connector J1 and fasten with the spring latches (11).
FOR 50MK6
(4)
Remove the blanking caps from the termination plug (3) and the WDB connector J4.
(5)
Carefully install the termination plug (3) to the WDB connector J4 and fasten with the spring latches (11).
FOR 50MK1, 50MK2, 50MK3, 50MK4
(6)
Put the insulation strip (15), the WDB (1) and the protective cover
(14) carefully into position.
(7)
Install the WDB (1) with the washers (8) and the screws (7).
R 1EFF : 051-099, 106-149, 201-299, 301-399, 1 23-33-47Page 415 1 1 May 01/05 1 1 1CES 1
(8)
Put the cable support (10) in position on top of the WDB (1) and install the washer (8) and the screw (9).
FOR 50MK5, 50MK6
(9)
Put the insulation strip (15), the WDB (1) and the protective cover
(14) carefully into position.
(10)
Install the WDB (1) with the washers (8) and the screws (7). FOR 50MK1, 50MK2, 50MK3, 50MK4, 50MK5, 50MK6
(11)
Remove the blanking caps from the electrical connectors (2) and the respective WDB connectors.
(12)
Connect the electrical connectors (2) to the WDB (1) and fasten with the spring latches (11).
R **ON A/C 106-149, 211-299, 301-399,
Subtask 23-33-47-420-050-A
B. Installation of the Wall Disconnect Box (WBD).
(1)
Make sure that the electrical connectors are clean and in the correct condition.
FOR 50MK5, 50MK6
(2)
Remove the blanking caps from the termination plug (3) and the WDB connector J4.
(3)
Carefully install the termination plug (3) to the WDB connector J4 and fasten with the spring latches (11).
FOR 50MK1, 50MK2, 50MK3, 50MK4, 50MK5, 50MK6
(4)
Put the insulation strip (15), the WDB (1) and the protective cover
(14) carefully into position.
(5)
Install the WDB (1) with the washers (8) and the screws (7).
(6)
Put the spacers (17 and 16) and the cable support (10) in position on top of the WDB (1) and install the washer (8) and the screw (9).
R 1EFF : 051-099, 106-149, 201-299, 301-399, 1 23-33-47Page 416 1 1 May 01/05 1 1 1CES 1
(7) Remove the blanking caps from the electrical connectors (2) and the respective WDB connectors.
(8) Connect the electrical connectors (2) to the WDB (1) and fasten with the spring latches (11).
R **ON A/C 051-099,
R Subtask 23-33-47-865-052-C
R R C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
R R R R -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2000VU PES MUSIC/CTL 21MK D01
R **ON A/C 106-149, 211-299,
Subtask 23-33-47-865-052-A
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2000VU PES/MUSIC/CTL 21MK D01 2000VU PES/MUSIC/CABIN/LH 23MK D02 2000VU PES/MUSIC/CABIN/RH 24MK D03
R 1EFF : 051-099, 106-149, 211-299, 301-399, 1 23-33-47Page 417 1 1 May 01/05 1 1 1CES 1
R **ON A/C 201-210,
R Subtask 23-33-47-865-052
R C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM Communications 通讯2(21)