 (3) Install the Electric Master Chip Detector (Ref. TASK 79-00-00-281-002).


 5. Close-up
________
 Subtask 79-35-00-410-053
 A. Close Access
 (1) Make sure that the work area is clean and clear of tool(s) and other items.

 (2) Close the fan cowl doors: (Ref. TASK 71-13-00-410-040) FOR 1000EM1 437AL, 438AR FOR 1000EM2 447AL, 448AR


 (3) Remove the warning notice(s). R
R (4) Make an entry in the log book.
R Subtask 79-35-00-862-051
R B. De-energize the ground service network (Ref. TASK 24-42-00-862-001).
 F 『 EEFF : ALL E Page 40779-35-00
 E E May 01/03 E E ECES E

 F  『
 E  C F M  E
 E  E
 E  56-5B  E
 E  E


 SWITCH - OIL FILTER DIFFERENTIAL PRESSURE (4001EN) - REMOVAL/INSTALLATION
_________________________________________________________________________ TASK 79-35-15-000-003 Removal of the Oil Filter Differential Pressure Switch
 1. Reason for the Job

__________________
 Self Explanatory


 2. Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific blanking plugs and caps No specific container 1l (0.25 USgal) No specific soft-nose connector pliers No specific warning notice
 B. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
71-13-00-010-040 Opening of the Fan Cowl Doors 79-35-15-991-300 Fig. 401
 3. Job Set-up
__________ Subtask 79-35-15-941-050
 A. Safety Precautions
 (1) On the center pedestal, on the ENG panel 115VU:

 (a) Put a warning notice to tell persons not to start the engine.

 (2) Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.


 F 『 EEFF : ALL E Page 40179-35-15
 E E Feb 01/98 E E ECES E

 F 『
 E C F M E
 E E
 E 56-5B E
 E E
 (3) On the overhead maintenance panel 50VU:

 (a) Make sure that the ON legend of the ENG/FADEC GND PWR/1(2) pushbutton switch is off.

 (b) Put a warning notice to tell persons not to energize the FADEC 1(2).


 Subtask 79-35-15-010-050
 B. Open the fan cowl doors: (Ref. TASK 71-13-00-010-040)
 FOR 1000EM1
 437AL, 438AR
 FOR 1000EM2
 447AL, 448AR

 4. Procedure
_________
 (Ref. Fig. 401/TASK 79-35-15-991-300)
 Subtask 79-35-15-020-050
 A. Removal of the Differential Pressure Switch
 (1) Disconnect the HJ7 harness connector (10) from the differential pressure switch (20). Use soft-nose connector pliers only if necessary.

 (2) Remove the bolts (50) which attach the differential pressure switch

 (20) to the lubrication unit.

 (3) Put a container 1l (0.25 USgal) below the differential pressure switch.

 (4) Remove the differential pressure switch (20) from the lubrication unit.

 (5) Remove and discard the O-rings (30) and (40).

 (6) Put blanking plugs and caps on the disconnected parts and orifice.


 F 『 EEFF : ALL E Page 40279-35-15
 E E Feb 01/98 E E ECES E F 『 E C F M E E E E 56-5B E

 

 Oil Filter Differential-Pressure-Switch
 Figure 401/TASK 79-35-15-991-300
 F EEFF :  ALL  『E 79-35-15 Page 403 
E  E  Feb 01/98
 E  E
 ECES  E


 F 『
 E C F M E
 E E
 E 56-5B E
 E E


 TASK 79-35-15-400-003
 Installation of the Oil Filter Differential Pressure Switch
 1. Reason for the Job
__________________
 Self Explanatory
 2. Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific soft-nose connector pliers
 No specific warning notice
 No specific Torque Wrench : range 35 to 45 lbf.in

 (0.39 to 0.50 m.daN)
 B. Consumable Materials