 -you can see a piece of the mark,
 -the silver sides of the yoke and the die holder are aligned with the end of the fitting. Carefully move the tool back until the end stops are approximately 0.8 mm (0.0314 in.) from the end of the fitting.

 (d)
 Make sure that the pressure relief valve of the swaging tool is set to open at 380 +17 -17 bar (5500 +250 -250 psi). Do not pressurize too high or too low. Operate the swaging tool with a hydraulic handpump or a hydraulic power source (push the remote air ON button). Keep the swaging tool in this position while you apply a hydraulic pressure of 380 +17 -17 bar (5500 +250 -250 psi). Remove the swaging tool from the fitting:


 -release the pressure,
 NOTE : If you do not release the pressure, the dies stay closed
____
 and you cannot remove them.

 -loosen the knurled nut and remove the power unit,
 -remove the die holder and yoke assembly.
 1EFF : ALL 1 20-23-11Page 260 1 1 Aug 01/04R 1 1 1CES 1


 Subtask 20-23-11-917-050
 E. Check of the Tube Joint
 (1)
 You must reject the joint if the tube:

 -goes too far into the fitting,
 -does not go sufficiently far into the fitting.

 (2)
 Look at the joint:

 -make sure that you can see a piece of the insertion mark.

 (3)
 Do an inspection of the joint with the applicable inspection gage. (Ref. Fig. 221/TASK 20-23-11-991-011, 222/TASK 20-23-11-991-012) The inspection gage must:


 -contain all the segments around the diameter of the fitting,
 -touch the end of the fitting with its shoulder. If the swaging is not correct, it is possible to swage the joint again, but not always.
 -------------------------------------------------------------------------------| INDICATION | POSSIBLE PROBLEM | CORRECTIVE ACTION | -------------------------------------------------------------------------------| The fitting does | The swaging pressure is | Make sure that the | | not swage | out of tolerances: | hydraulic power supply | | correctly. | FOR TOOLS SERIES DLT: | and connections to the | | | - 10000 +250 -250 psi | tool are correct. | | | FOR TOOL SERIES D12000: | | | | - 5500 +250 -250 psi | | | | | | | | The swaging head is too | Use the correct swaging | | | large. | head. | | | | | | The gage does not | The swaging pressure is not | Do the swage again. | | go on top of the | correct. | | | external diameter | | | | of the swaged | | | | fitting. | | | | | | | | | The gage is on top of the | Turn the gage away from | | | flash marks. | the flash marks. | | | The dies and the walls of | Carefully remove the dies | | | the yoke and the die holder | from the head and clean | | | must be clean. | the dies and all parts of | | | | the head assembly. | | | | | | The shoulder of | You did not push the fitting| Do the swage again. | | the gage does not | sufficiently far into the | |
 1EFF : ALL 1 20-23-11Page 261 1 1 Aug 01/04R 1 1 1CES 1


 Inspection Gage Figure 221/TASK 20-23-11-991-011
 1EFF : 1 1R 1CES  ALL  1 11 1 20-23-11 Page 262 Aug 01/03

 

 Swaged Fitting Installation Figure 222/TASK 20-23-11-991-012
 1EFF : 1 1R 1CES  ALL  1 11 1 20-23-11 Page 263 Aug 01/03

 

 -------------------------------------------------------------------------------| INDICATION | POSSIBLE PROBLEM | CORRECTIVE ACTION | -------------------------------------------------------------------------------| touch the end of | swaging head. | | | the fitting. | | | | | | | | You cannot see the| The insertion mark on the | Cut out the fitting. | | insertion mark or | tube was not aligned with | | | you can see all | the end of the fitting du-| | | the mark. | ring swaging. | | -------------------------------------------------------------------------------
NOTE : For any other malfunctions, contact your PERMASWAGE S.A.
____
 supplier.

 Subtask 20-23-11-860-065
 F. Put the aircraft back to its initial configuration.
 (1)
 Pressurize the hydraulic reservoirs (Ref. TASK 29-14-00-614-002).

 (2)
 If necessary, fill the hydraulic reservoirs:

 -with a hand pump (Ref. TASK 12-12-29-611-001) - or with a hydraulic cart (Ref. TASK 12-12-29-611-002)

 (3)
 Pressurize the hydraulic systems:

 -
for the Green system (Ref. TASK 29-10-00-863-001)

 -
for the Yellow system (Ref. TASK 29-10-00-863-002)

 -
for the Blue system (Ref. TASK 29-10-00-863-003).

 

 (4)
 Make sure that there is no leakage in the repaired area.

 (5)
 Bleed the related hydraulic system:

 (a)
 For the Green system:
 