Section 1 – Introduction
Preferably limited to general statements about the facility and to report objectives.
Section 2 – Management Summary
To include statements on the completion of design and operability assessment activities, completion of helideck hook-up and commissioning activities and overall conclusions on the helideck operational status and acceptability.
Section 3 – Documentation
Provide listings of key helideck project and vendor design drawings, design specifications, data sheets and reports (e.g. helideck wind tunnel testing). The information that is provided for each document should include the Document number, Originator, Title, Revision and Approval status and date.
Section 4 – Logistics & Operations Philosophy
Following a brief introduction, the contents of this section should address the installation, MODU or vessel operator's preferred or specific aircraft selection, routings and payload expectations. Diversion and adverse weather polices should be included along with relevant information on intended search & rescue provisions / coverage and a statement on adverse weather policy. The field operator’s requirements (taken from initial design specification) for the helideck and facilities should be noted along with any variations requested as design proceeds. Additionally, the installation / vessel operator’s requirements for helicopter refuelling, passenger and freight handling should be noted. Finally, a brief statement covering the installation / vessel operator’s existing facilities and operating experience should be included.
Section 5 – Regulatory Requirements and Verification Process
This section should briefly set out the regulations, rules, codes and standards that are applicable to the helideck design, fabrication, construction and verification processes. It is also prudent to identify each of the ‘official’ bodies concerned with the verification of the helideck, its support facilities and their areas of involvement. This process is usually simple for UK fixed installations but, in the case of FPSOs, MODUs and vessels, which may retain class for world-wide operations, it can be more complicated. It is therefore essential to identify the classification aspects, which introduce the need to observe international conventions that may conflict with established UK offshore requirements.
Verification meetings and the initial BHAB Helidecks review and inspection should be noted. Reference to the outcomes and outstanding work lists should be included.
Section 6 – Design and Operability Review
This section should address the whole range of topics relevant to the helideck design and its future safe operation. Sub-sections should cover the following:
1. Production and Operating Environments
Includes field / operating location(s), environmental conditions, the facility layout and leading particulars, production processes and helideck / helicopter transportation risk assessments.