Part
Classification
Category
Customer FAIR
Review
Required
Note
New base part number or first time
supplied by source FULL All YES
New dash number(s) issued and
manufactured. See note if new dash
number affects 10 or less features of
the last full FAIR
FULL All YES
Consult FQE to
request partial FAIR
per AS9102
The engineering drawing for the part
receives a revision letter change and
part has a Honeywell approved
FAIR in the last 3 years
PARTIAL All YES
Current FAIR conditionally accepted
based on Deviation, RMRA, Case
Record, MRB or Manufacturing
Revision authorizing rework or
requirement modification
PARTIAL
FAIR due on
next lot
manufactured or
expiration of
deviation/waiver
All
Confirm with
Honeywell site if
customer approval
is required
A change in process, material, tooling,
or inspection method that can
potentially affect form, fit, or function PARTIAL All
Confirm with
Honeywell site if
customer approval
is required
SPOCs 110, 180
and/or Spec. may
contain additional
requirements
A change in manufacturing source or
location of manufacturing equipment,
including tooling transferred from
another Supplier or division of the
same supplier
FULL All
Confirm with
Honeywell site if
customer approval
is required
Consult FQE to
request partial FAIR
per AS9102
Aerospace
Supplemental Purchase Order Conditions (SPOC) Manual
UNCONTROLLED IN HARDCOPY
Revision H Effective Date: 15 January 2009 15
Table 2 – FAIR Frequency Requirements
Frequency of FAIR is based on the number of production pieces since the last approved FAIR. The Supplier shall
assure that all Event Table 1 conditions have been satisfied prior to usage of the Casting Tool Life Management Table
below. Frequencies are, at a minimum, tracked by the Supplier/Manufacturer and do not relieve the Supplier of the
responsibility/liability to meet the drawing and/or authorized deviation. The Supplier is required to establish and
maintain written procedures to assure compliance with these frequencies.
Table 3 – Casting Tool Life Management
Part Type / Process / Pattern
Frequency of FAIR based on number
of pieces produced by tool since date
of last full FAIR
Solid Blades / Vanes / Investment 50,000
Cored Blades / Investment 25,000
Nozzle Segment / Investment 10,000
Small Structure / Investment (NO dim/dia. OVER 19.999 inches) 10,000
Die-casting 10,000
Wheels / Investment 5,000
360 Nozzles / Investment 5,000
Large Structure / Investment (ANY dim/dia. 20.000 inches or over) 2,000
Metal / Sand 1,000
P-Mold 1,000
Plastic / Sand
Note: Tooling made from combined materials default to plastic frequency. 800
Wood / Sand 350
Event Description FAIR
type due
FAIRTRACKER
Part Classification
Category
Customer
FAIR Review
Required
Note
Two year (2) lapse in
production FULL All YES
Three years since Full FAIR
(except castings) FULL II,III YES See 124.3
Casting tool reaches Table 3
usage levels
FULL All
Confirm with
Honeywell site if
customer
approval is
required
See 124.5
For Stock / Inventory
hardware that was
manufactured in the time
frame represented by a
Honeywell approved FAIR
N/A All
NO
Issue FAIR Delay
(AF0114 form) until next
production run. FQE
approval required. Follow
Conditional FAIR
guidance 124.2 for
FAIRTRACKER loading.
Aerospace
Supplemental Purchase Order Conditions (SPOC) Manual
UNCONTROLLED IN HARDCOPY
Revision H Effective Date: 15 January 2009 16
124.5 MPC Exemptions for Periodic/Repeat FAIRS
Category II parts may be exempt from the Honeywell periodic/repeat FAIR requirement if the following conditions have
been met: 1) An MPC Control Plan is in place for the part (described in SPOC 410) and has been validated by a
Honeywell Representative, and 2) No part quality escapes to Honeywell for this part number have occurred in the past
12 months.
To be granted an MPC exception, the supplier shall complete form AF0115 at the end of the FAIR exemption period
attesting that the criteria above have been achieved and to record FQE concurrence. AF0115 from is available from
the Field Quality Engineering group as well as the Aerospace Supplier Portal.
124.6 Approvals
When a Customer FAIR Review is required per Tables 1 or 2, a Honeywell Field Quality Engineer (or a Honeywelldelegated
 