 S 914-007
 (1)  
Read and obey the safety precautions and general instructions before you do the maintenance (AMM 35-00-00/201).

 S 034-002

 (2)
Remove the snap ring from the overbaord discharge indicator.

 (3)  
Remove the damaged plastic disc or particles.


 S 024-003
 TASK 35-11-10-404-004
 3.  Overboard Discharge Indicator Installation (Fig. 401)__________________________________________
 A.  References
 (1)  
AMM 35-00-00/201, Oxygen

 (2)  
IPC 35-11-10


 B.  Access
 (1)  Location Zone 124 Forward Cargo Container Compartment, Aft Half Right
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 35-11-10
 ALL  ú ú 01 Page 401 ú Oct 18/01
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400
MAINTENANCE MANUAL


OVERBOARD DISCHARGE INDICATOR


Overboard Discharge Indicator Installation
Figure 401

EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 35-11-10
 ALL  ú ú 01 Page 402 ú Feb 10/94
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 C. Procedure
 S 914-008
 (1)  
Read and obey the safety precautions and general instructions before you do the maintenance (AMM 35-00-00/201).

 S 214-012

 (2)  
If there was a ruptured overboard discharge indicator event that had left the discharge line exposed for an extended period of time, do the steps that follow:

 (a)  
Inspect the crew and passenger oxygen cylinders, replace the frangible disc on the cylinder safety valve with a ruptured frangible disc.

 (b)  
Flush the overboard discharge and vent lines with 100 psi dry clean air or nitrogen.

 


 NOTE: Make sure there is no oil contamination in the air or
____
 nitrogen source.

 S 424-005
 (3)  
Insert the plastic disc in the port.

 (4)  
Install the snap ring.


 S 434-006
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 35-11-10
 ALL  ú ú 02 Page 403 ú Feb 18/02
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 VOLTAGE AVERAGING UNIT - REMOVAL/INSTALLATION
_____________________________________________
 1.  General_______
 A.  These tasks are included in this procedure:
 (1)  
Removal of the voltage averaging unit.

 (2)  
Installation of the voltage averaging unit.


 B.  The voltage averaging unit is installed in the ceiling beam aft of the cargo door in the forward cargo compartment. Access to the voltage averaging unit is through the access panels for the passenger oxgyen cylinders.
 TASK 35-11-12-004-001
 2.  Voltage Averaging Unit Removal (Fig. 401)______________________________
 A.  References
 (1)  
AMM 35-00-00/201, Oxygen

 (2)  
IPC 35-11-12


 B.  Access
 (1)  Location Zone 124 Forward Cargo Container Compartment, Aft Half Right
 C.  Procedure
 S 914-014
 (1)  
Read and obey the safety precautions and general instructions before you do the maintenance (AMM 35-00-00/201).

 S 864-002

 (2)  
Open this circuit breaker and attach a DO-NOT-CLOSE tag:


 (a)  P7 Overhead Circuit Breaker Panel
 1) 7D4 OXYGEN VALVE & IND

 S 014-003
 (3)  
Open the cylinder access panel which is attached by snaps and velcro tape.

 S 034-004

 (4)  
Disconnect the DM992 electrical connector from the voltage averaging unit (M992).
 