(17)
Do the test of the pitot probe (9DA1, 9DA2, 9DA3) without the CFDS (Ref. TASK 34-11-15-710-001).
(18)
Do the operational test of the APU (GTCP 36-300) (Ref. TASK 49-00-00-710-004).
(19)
Do the operational test of the APU (APS 3200) (Ref. TASK 49-00-00-710-008).
(20)
Do the operational test of the APU (131-9(A)) (Ref. TASK 49-00-00-710-010).
Subtask 31-10-00-710-060 R L. Test Program after Removal/Installation of the Panel 27VU
(1)
Do the operational test of the passenger entertainment system (music) (Ref. TASK 23-33-00-710-002).
(2)
Do the operational test of the passenger entertainment (video) (Ref. TASK 23-36-00-710-001).
1EFF : ALL 1 31-10-00Page 210 1 1 Feb 01/03 1 1 1CES 1
Subtask 31-10-00-710-061 R M. Test Program after Removal/Installation of the Panel 30VU
(1)
Do the operational test of the flow control and indicating system (Ref. TASK 21-51-00-710-002).
(2)
Do the operational test of the flow control valves closing (Ref. TASK 21-51-00-710-003).
(3)
Do the operational test of the emergency ram-air inlet (Ref. TASK 21-55-00-710-001).
(4)
Do the functional test of the cockpit and cabin temperature control without CFDS/MCDU (Ref. TASK 21-63-00-720-001).
(5)
Do the operational test of the bleed air system (Ref. TASK 36-11-00-710-003).
Subtask 31-10-00-710-062 R N. Test Program after Removal/Installation of the Panel 35VU
(1)
Do the operational test of the Integrated Drive Generator (IDG) disconnect and reconnect function (Ref. TASK 24-21-00-710-040). (CFM)
(2)
Do the operational test of the Integrated Drive Generator (IDG) disconnect and reconnect function (Ref. TASK 24-21-00-710-042). (IAE)
(3)
Do the operational test of the transfer inhibition (Ref. TASK 24-22-00-710-002).
(4)
Do the operational test of the AC essential generation switching (Ref. TASK 24-25-00-710-001).
(5)
Do the operational test of the manual and automatic shedding of the galleys (Ref. TASK 24-26-00-710-001).
(6)
Do the operational test of the static inverter (3XB) when the aircraft electrical circuits are energized from the external power (Ref. TASK 24-28-00-710-001).
(7)
Energize the aircraft electrical circuits from the external power (Ref. TASK 24-41-00-861-002).
(8)
Do the operational test of the Ground Power Control Unit (GPCU) (Ref. TASK 24-41-00-740-002).
1EFF : ALL 1 31-10-00Page 211 1 1 Feb 01/03 1 1 1CES 1
(9) Do the operational test of the Ground Auxiliary Power Control Unit (GAPCU) (Ref. TASK 24-41-00-740-002).
(10) Do the operational test of the galley supply (Ref. TASK 24-56-00-710-001).
Subtask 31-10-00-710-063 R P. Test Program after Removal/Installation of the Panel 40VU
(1)
Do the operational test of the center tank pump control (Ref. TASK 28-21-00-710-010).
(2)
Do the operational test of the wing-tank fuel control (Ref. TASK 28-21-00-710-001).
(3)
Do the operational test of the crossfeed valve (Ref. TASK 28-23-00-720-001).
(4)
Do the operational test of the main transfer system (Ref. TASK 28-26-00-710-001).
(5)
Do the operational test of the ACT manual transfer system (Ref. TASK 28-28-00-710-001).
(6)
Do the functional test of the hydraulic fire shut-off valves 1046GK and 3046GD (Ref. TASK 29-10-00-720-001).
(7)
Do the operational test of the manual deployment and the retraction of the Ram Air Turbine (Ref. TASK 29-22-00-710-003).
(8)
Do the operational test of the manual deployment and the retraction of the Ram Air Turbine (Ref. TASK 29-22-00-710-007).
Subtask 31-10-00-710-090 R Q. Test Program after Removal/Installation of the Panel 45VU
(1) Do the operational test of the cockpit door lock system (CDLS) (Ref. TASK 52-51-00-710-002).
Subtask 31-10-00-710-064 R R. Test Program after Removal/Installation of the Panel 48VU
(1) Do the operational test of the Audio Management Unit (Ref. TASK 23-51-00-710-001).
1EFF : ALL 1 31-10-00Page 212 1 1 Feb 01/03 1 1 1CES 1 Subtask 31-10-00-710-065
S. Test Program after Removal/Installation of the Panel 50VU
(1)
Do the operational test of the service interphone (Ref. TASK 23-44-00-700-001).
(2)
Do the operational test of the CVR (Ref. TASK 23-71-00-710-001).
(3)
Do the functional test of the erase section of the CVR (Ref. TASK 23-71-00-720-002).