S 212-013
 (4)  
If the valve that follows was open during a volcanic ash fallout, clean the total Equipment Cooling System (AMM 21-58-00).
 (a)  Equipment Cooling Overboard Exhaust Valve.
 S 162-014
 (5)  
Clean the primary and secondary heat exchangers as necessary (AMM 21-51-02).
 (6) 
Remove the primary Water Extractor for examination (AMM 21-51-04).
 S 022-015
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
 05-51-31
 ALL  ú ú 01 Page 204 ú Sep 28/01 
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details. 
A
757 
MAINTENANCE MANUAL
 (7)  S 162-016If volcanic ash is found in the water extractor, clean the Primary Water Extractor as necessary. 
 (8)  S 022-017Remove the Secondary Water Extractor for examination (AMM 21-51-21). 
 (9)  S 162-018If volcanic ash is found in the water extractor, clean the Secondary Water Extractor as necessary. 
 S 022-019
 (10)
 Remove the pack Flow Control and Shutoff Valves for examination (AMM 21-51-01).
S 212-020
 (11)
 Examine the pack Flow Control and Shutoff Valves for signs of volcanic ash (AMM 21-51-01).
S 022-021
 (12)
 Remove the pack Heat Exchangers for examination (AMM 21-51-02).
S 212-022
 (13)
 Examine the pack Heat Exchangers for signs of volcanic ash (AMM 21-51-02).
S 022-023
 (14)
 Remove the Equipment Cooling Air Filters for examination (AMM 21-58-07).
S 022-025
 (15)
 Remove the Recirculating Air Fans for examination (AMM 21-25-01/401)
S 022-026
 (16)
 Examine the Recirculating Air Fans for signs of volcanic ash (AMM 21-25-01/401).
S 212-027
 (17)
 Examine the Recirculation Air Filters for volcanic ash (AMM 21-25-02/401).
S 022-028
 (18)
 Remove the Cabin Pressure Outflow Valve for examination (AMM 21-31-03).
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
 05-51-31
 ALL  ú ú 03 Page 205 ú May 28/99 
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details. 
A 
757 MAINTENANCE MANUAL
 S 212-029
 (19)
 Examine the Cabin Pressure Outflow Valve for volcanic ash (AMM 21-31-03).
S 022-030
 (20)
 Remove the actuator for the Cabin Pressure Outflow Valve for examination (AMM 21-31-04).
S 212-031
 (21)
 Examine the actuator for the Cabin Pressure Outflow Valve for volcanic ash (AMM 21-31-04).
S 022-032
 (22)
 Remove the Cabin Air Supply Check Valves for examination (AMM 21-51-15).
S 212-033
 (23)
 Examine the Cabin Air Supply Check Valves for volcanic ash (AMM 21-51-15).
S 212-034
 (24)
 Examine the Overboard Exhaust Valve for volcanic ash.  If the valve was closed, remove the volcanic ash from the external surface (AMM 21-58-05).
S 022-035
 (25)
 If the Overboard Exhaust Valve was open, remove the valve (AMM 21-58-05).
S 022-036
 (26)
 Remove the Recirculation Air Check Valve for examination (AMM 21-25-03).
S 212-037
 (27)
 Examine the Recirculation Air Check Valve for volcanic ash (AMM 21-25-03).
S 022-038
 (28)
 Remove the Positive Pressure Relief Valve for examination (AMM 21-32-01).
S 212-039
 (29)
 Examine the Positive Pressure Relief Valve for volcanic ash (AMM 21-32-01).
S 022-040
 (30)
 Remove the Vacuum Pressure Relief Valve for examination (AMM 21-32-02).
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
 05-51-31
 ALL  ú ú 03 Page 206 ú May 28/99 
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:757 AMM 飞机维护手册 时间限制/维护检查(49)